2016 W 93RD ST 90047
Certificate Information: 2016 W 93RD ST 90047
- Application / Permit
- 22014-10000-05243
- Plan Check / Job No.
- B22LA19521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan NEW ADDITION TO S.F.D.
- Permit Issued
- Issued on 4/4/2023
- Issuing Office
- Current Status
- CofO Issued on 1/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | JAD BASMA |
| Corrections Issued | 10/27/2022 | JAD BASMA |
| Quality Review Completed | 11/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 2/15/2023 | JAD BASMA |
| Applicant returned to address corrections | 2/28/2023 | JAD BASMA |
| Plan Check Approved | 3/17/2023 | JAD BASMA |
| Issued | 4/4/2023 | LINDA KHA |
| CofO in Progress | 1/3/2024 | ENRIQUE MIRELES |
| Permit Finaled | 1/7/2024 | DEROLD HAUFF |
| CofO Issued | 1/7/2024 | DEROLD HAUFF |
| Permit Finaled | 1/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/12/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 2/6/2023 | CINDY QI |
Contact Information
| Contractor | Blue Dog Renovations Llc; Lic. No.: 1093494-B | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: NA35693 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/5/2023 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/11/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/31/2023 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/10/2023 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/10/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 10/10/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/10/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 10/19/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/19/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/1/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/1/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/14/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/14/2023 | Approved | ENRIQUE MIRELES |
| Final | 12/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/14/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 12/14/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 12/14/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 12/14/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 12/14/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/14/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/22/2023 | Approved | ENRIQUE MIRELES |
| Final | 12/22/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| HVAC-Final | 12/22/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 12/22/2023 | Approved | ENRIQUE MIRELES |