8718 1/2 S MENLO AVE 90044

Certificate Information: 8718 1/2 S MENLO AVE 90044

Application / Permit
22014-10000-05237
Plan Check / Job No.
B22LA21427
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (E) GARAGE 361 SQ.FT. TO BE CONVERTED TO (N) ADU AND (N) ADDITION 240 SQ.FT. TO (N) ADU. PER LAMC 12.22 A.33(C) AND(D). PER WFPP
Permit Issued
Issued on 3/6/2023
Issuing Office
Current Status
CofO in Progress on 4/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 10/31/2022 ALFREDO JARA
Corrections Issued 11/1/2022 ALFREDO JARA
Applicant returned to address corrections 11/15/2022 ALFREDO JARA
Applicant returned to address corrections 11/18/2022 JASON JANGADA
Plan Check Approved 3/6/2023 ALFREDO JARA
Issued 3/6/2023 APPLICANT
CofO in Progress 6/7/2023 STUART CHAPMAN
No Progress 4/6/2025 DEROLD HAUFF
CofO in Progress 4/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 11/2/2022 MICHAEL SOTO
Address approval Cleared 11/5/2022 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 11/5/2022 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 11/21/2022 ADRIAN SANCHEZ
Sewer availability Cleared 11/21/2022 ADRIAN SANCHEZ
Construction near power lines Cleared 2/24/2023 RIDWAN HARDY

Contact Information

Contractor New Beginning Construction Company Corp The; Lic. No.: 848904-B       ,
Contractor New Beginnning Construction Company The; Lic. No.: 848904-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/14/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 3/14/2023 Partial Approval LILIANA PORTILLO
Sewer 3/14/2023 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 3/16/2023 Approved LILIANA PORTILLO
Sewer 3/16/2023 Approved LILIANA PORTILLO
Underground Mechanical 3/16/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 4/10/2023 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 4/10/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/10/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 4/10/2023 Approved ALIZAH MAYAGOITIA
Wood Frame 4/10/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/12/2023 Approved LILIANA PORTILLO
Insulation 4/12/2023 Approved LILIANA PORTILLO
Shower Pan 4/12/2023 Approved LILIANA PORTILLO
Drywall Nailing 4/14/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/14/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/30/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/30/2023 Approved MICHAEL LEWIS
Final 5/30/2023 Corrections Issued MICHAEL LEWIS
Gas Test 5/30/2023 Approved MICHAEL LEWIS
Green Building Final 5/30/2023 Approved MICHAEL LEWIS
Green Building Rough 5/30/2023 Approved MICHAEL LEWIS
HVAC-Final 5/30/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 5/30/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 5/30/2023 Corrections Issued MICHAEL LEWIS
Smoke Detectors 5/30/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 6/6/2023 Approved STUART CHAPMAN
Final 6/6/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 6/6/2023 Approved STUART CHAPMAN
Service/Power Release 6/6/2023 Approved STUART CHAPMAN