8718 1/2 S MENLO AVE 90044
Certificate Information: 8718 1/2 S MENLO AVE 90044
- Application / Permit
- 22014-10000-05237
- Plan Check / Job No.
- B22LA21427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan (E) GARAGE 361 SQ.FT. TO BE CONVERTED TO (N) ADU AND (N) ADDITION 240 SQ.FT. TO (N) ADU. PER LAMC 12.22 A.33(C) AND(D). PER WFPP
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Current Status
- CofO in Progress on 4/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2022 | ALFREDO JARA |
| Corrections Issued | 11/1/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 11/15/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 11/18/2022 | JASON JANGADA |
| Plan Check Approved | 3/6/2023 | ALFREDO JARA |
| Issued | 3/6/2023 | APPLICANT |
| CofO in Progress | 6/7/2023 | STUART CHAPMAN |
| No Progress | 4/6/2025 | DEROLD HAUFF |
| CofO in Progress | 4/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/2/2022 | MICHAEL SOTO |
| Address approval | Cleared | 11/5/2022 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/5/2022 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 11/21/2022 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 2/24/2023 | RIDWAN HARDY |
Contact Information
| Contractor | New Beginning Construction Company Corp The; Lic. No.: 848904-B | , |
| Contractor | New Beginnning Construction Company The; Lic. No.: 848904-B | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/14/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 3/14/2023 | Partial Approval | LILIANA PORTILLO |
| Sewer | 3/14/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/16/2023 | Approved | LILIANA PORTILLO |
| Sewer | 3/16/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 3/16/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/10/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/10/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/10/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/10/2023 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 4/10/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/12/2023 | Approved | LILIANA PORTILLO |
| Insulation | 4/12/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 4/12/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 4/14/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/14/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/30/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 5/30/2023 | Approved | MICHAEL LEWIS |
| Final | 5/30/2023 | Corrections Issued | MICHAEL LEWIS |
| Gas Test | 5/30/2023 | Approved | MICHAEL LEWIS |
| Green Building Final | 5/30/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 5/30/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 5/30/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 5/30/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 5/30/2023 | Corrections Issued | MICHAEL LEWIS |
| Smoke Detectors | 5/30/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/6/2023 | Approved | STUART CHAPMAN |
| Final | 6/6/2023 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 6/6/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 6/6/2023 | Approved | STUART CHAPMAN |