765 W 108TH ST 90044
Certificate Information: 765 W 108TH ST 90044
- Application / Permit
- 22014-10000-05232
- Plan Check / Job No.
- B22LA21407
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to rear of (E) 1-story SFD Room addition
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | VICTOR CHEN |
| Corrections Issued | 11/7/2022 | VICTOR CHEN |
| Building Plans Picked Up | 11/16/2022 | APPLICANT |
| Plan Check Approved | 12/12/2022 | RAHEL BEYENE |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 1/12/2024 | JAMES CHAVEZ |
| CofO Issued | 1/12/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/12/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/23/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | AMAAN MALIK |
Contact Information
| Contractor | C G S Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 2/1/2023 | Approved | JOHN KLARIN |
| Underground Mechanical | 2/27/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/2/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 6/2/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Wood Frame | 6/2/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 6/13/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 7/6/2023 | Corrections Issued | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/27/2023 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/2/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 8/2/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 8/2/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/2/2023 | Partial Inspection | JAMES CHAVEZ |
| Insulation | 8/9/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 8/18/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 8/18/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 8/18/2023 | Partial Approval | JAMES CHAVEZ |
| Interior/Exterior Lathing | 9/7/2023 | Approved | JOHN KLARIN |
| Shower Pan | 9/7/2023 | Approved | JOHN KLARIN |
| Final | 12/20/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/20/2023 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/20/2023 | Approved | JOHN KLARIN |
| Final | 1/8/2024 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 1/8/2024 | Approved | JAMES CHAVEZ |