765 W 108TH ST 90044

Certificate Information: 765 W 108TH ST 90044

Application / Permit
22014-10000-05232
Plan Check / Job No.
B22LA21407
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of (E) 1-story SFD Room addition
Permit Issued
Issued on 12/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 VICTOR CHEN
Corrections Issued 11/7/2022 VICTOR CHEN
Building Plans Picked Up 11/16/2022 APPLICANT
Plan Check Approved 12/12/2022 RAHEL BEYENE
Issued 12/16/2022 APPLICANT
CofO in Progress 1/12/2024 JAMES CHAVEZ
CofO Issued 1/12/2024 ANSON MAGLASANG
Permit Finaled 1/12/2024 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/23/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 11/29/2022 AMAAN MALIK

Contact Information

Contractor C G S Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/1/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 2/1/2023 Approved JOHN KLARIN
Underground Mechanical 2/27/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 6/2/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 6/2/2023 Not Ready for Inspection JAMES CHAVEZ
Wood Frame 6/2/2023 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 6/13/2023 Approved JAMES CHAVEZ
HVAC-Rough 7/6/2023 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 7/27/2023 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 8/2/2023 Approved JAMES CHAVEZ
Green Building Rough 8/2/2023 Approved JAMES CHAVEZ
HVAC-Rough 8/2/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 8/2/2023 Partial Inspection JAMES CHAVEZ
Insulation 8/9/2023 Approved JAMES CHAVEZ
Drywall Nailing 8/18/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 8/18/2023 Approved JAMES CHAVEZ
Shower Pan 8/18/2023 Partial Approval JAMES CHAVEZ
Interior/Exterior Lathing 9/7/2023 Approved JOHN KLARIN
Shower Pan 9/7/2023 Approved JOHN KLARIN
Final 12/20/2023 Corrections Issued JOHN KLARIN
Green Building Final 12/20/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 12/20/2023 Approved JOHN KLARIN
Final 1/8/2024 OK to Issue CofO JAMES CHAVEZ
Green Building Final 1/8/2024 Approved JAMES CHAVEZ