3811 S MUIRFIELD ROAD 90008
Certificate Information: 3811 S MUIRFIELD ROAD 90008
- Application / Permit
- 22014-10000-05200
- Plan Check / Job No.
- B22LA21242
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel to dwelling. Rear addition of new bedroom and bathroom. Extension of living room area.
- Permit Issued
- Issued on 11/23/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2022 | JOSEPH RAFOLS |
| Corrections Issued | 10/26/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 11/1/2022 | APPLICANT |
| Plan Check Approved | 11/14/2022 | RICARDO RAMIREZ |
| Issued | 11/23/2022 | APPLICANT |
| CofO in Progress | 12/7/2023 | ANTHONY EGSON |
| Permit Finaled | 12/28/2023 | DEROLD HAUFF |
| CofO Issued | 12/28/2023 | DEROLD HAUFF |
| Permit Finaled | 12/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/8/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 11/8/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2022 | TREVOR QUAN |
Contact Information
| Contractor | Oran Remodeling Inc; Lic. No.: 1086123-B | 14829 MORRISON ST SHERMAN OAKS, CA 91403 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/5/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/9/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/14/2022 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/10/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 1/10/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 1/10/2023 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/13/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/13/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/13/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/13/2023 | Approved | ANTHONY EGSON |
| Insulation | 1/30/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/30/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 1/30/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/6/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 2/6/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/11/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 5/11/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/11/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 5/11/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 5/11/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 5/11/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 5/11/2023 | Approved | ANTHONY EGSON |
| Final | 11/7/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 11/7/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/16/2023 | Approved | ANTHONY EGSON |
| Final | 11/16/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 11/16/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 11/16/2023 | Approved | ANTHONY EGSON |
| Final | 12/6/2023 | OK to Issue CofO | ANTHONY EGSON |