9848-9850 N HILLHAVEN AVE 91042

Certificate Information: 9848-9850 N HILLHAVEN AVE 91042

Application / Permit
22014-10000-05199
Plan Check / Job No.
B22LA21241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major interior remodel and second-Story addition to (E) one-story Single Family Dwelling with attached carport New ground-floor addition to SFD and new attached adu per ordinance LAMC 12.22 A.33(c) and (e) NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 4/18/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 JAD BASMA
Corrections Issued 11/18/2022 JAD BASMA
Quality Review Completed 11/30/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/2/2022 APPLICANT
Plan Check Approved 4/16/2024 JAD BASMA
Issued 4/18/2024 APPLICANT
CofO in Progress 4/14/2026 NICHOLAS TROWBRIDGE
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/7/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 12/8/2022 ROMAN GUTIERREZ
Sewer availability Cleared 12/8/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 12/15/2022 ANTHONY VARGAS
Hydrant and Access approval Cleared 12/16/2022 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 1/10/2023 ROMAN GUTIERREZ
Specific Plan Cleared 4/2/2024 JOSHUA ORDONEZ
GPI Written Notices Cleared 4/16/2024 JAD BASMA
Grading Pre-Inspection Cleared 4/16/2024 JAD BASMA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/12/2024 Not Ready for Inspection ROY SPAULDING
Sewer 7/12/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 7/16/2024 Partial Approval WILLIAM WREN
Sewer 7/16/2024 Approved WILLIAM WREN
Sewer 7/18/2024 Approved WILLIAM WREN
Footing/Foundation/Slab 7/25/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Partial Approval DAVID ANDERSON
Deputy Wood Construction 10/28/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 12/19/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 1/16/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 1/16/2025 Approved WILLIAM WREN
Green Building Rough 1/16/2025 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 1/16/2025 Not Ready for Inspection WILLIAM WREN
MERV13>=Rough 1/16/2025 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 1/16/2025 Approved WILLIAM WREN
Verify Sprinkler Sign Off 1/16/2025 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 1/21/2025 Approved WILLIAM WREN
Green Building Rough 1/21/2025 Approved WILLIAM WREN
HVAC-Rough 1/21/2025 Approved WILLIAM WREN
MERV13>=Rough 1/21/2025 Approved WILLIAM WREN
Verify Sprinkler Sign Off 1/21/2025 Approved WILLIAM WREN
Insulation 2/7/2025 Approved WILLIAM WREN
Drywall Nailing 2/19/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 2/28/2025 Approved MICHAEL CORTEZ
Shower Pan 2/28/2025 Approved MICHAEL CORTEZ
Final 3/27/2026 Corrections Issued MICHEL ABAJAN
Green Building Final 3/27/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/27/2026 Approved MICHEL ABAJAN
Final 4/7/2026 Corrections Issued NICHOLAS TROWBRIDGE
MERV13>=Final 4/7/2026 Approved NICHOLAS TROWBRIDGE
Final 4/10/2026 OK to Issue CofO NICHOLAS TROWBRIDGE