10558 W PUTNEY ROAD 90064
Certificate Information: 10558 W PUTNEY ROAD 90064
- Application / Permit
- 22014-10000-05198
- Plan Check / Job No.
- B22LA21235
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN 1. REMODEL TO (E) SFD WITH ATTACHED GARAGE. NO CHANGE TO OVERALL BLDG FOOTPRINT.
- Permit Issued
- Issued on 12/26/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/28/2026
Permit Application Status History
| Submitted | 11/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | ADRIANA LOPEZ |
| Corrections Issued | 12/6/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 12/15/2022 | GARO TELMI |
| Plan Check Approved | 9/25/2023 | ADRIANA LOPEZ |
| No Progress | 12/18/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 12/18/2024 | ADRIANA LOPEZ |
| Issued | 12/26/2024 | APPLICANT |
| Permit Finaled | 1/27/2026 | ASHLEY THOMPSON |
Permit Application Clearance Information
| ZI | Cleared | 12/20/2022 | ANACANY HURTADO |
| Roof/Waste drainage to street | Cleared | 12/22/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 12/22/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 1/4/2023 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | K T Construction & Development; Lic. No.: 1031495-B | 137 SOUTH ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Mansuri,, Mehran; Lic. No.: C78614 | 14944 HESBY ST SHERMAN OAKS, CA 91403 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/13/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/14/2025 | Approved | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 1/22/2025 | Conditional Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/3/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/3/2025 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 2/3/2025 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 2/13/2025 | Conditional Approval | DANIEL VERA |
| Deputy Wood Construction | 2/13/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Partial Approval | DANIEL VERA |
| HVAC-Rough | 2/13/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 2/13/2025 | Partial Approval | DANIEL VERA |
| Wood Frame | 2/13/2025 | Conditional Approval | DANIEL VERA |
| Insulation | 2/18/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 2/21/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/24/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 3/24/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/24/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 4/2/2025 | Conditional Approval | STEPHANIE SWANSON |
| Insulation | 4/2/2025 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/15/2026 | Corrections Issued | ASHLEY THOMPSON |
| Final | 1/15/2026 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 1/15/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 1/15/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 1/15/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/27/2026 | Approved | ASHLEY THOMPSON |
| Final | 1/27/2026 | Permit Finaled | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 1/27/2026 | Approved | ASHLEY THOMPSON |