3824 S HARVARD BLVD 90062
Certificate Information: 3824 S HARVARD BLVD 90062
- Application / Permit
- 22014-10000-05194
- Plan Check / Job No.
- B22LA21217
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN 1) MAIN HOUSE ADDITION (389 S.F IRREGULAR SHAPE 21'6" X 27'3") ) - ONE BEDROOM, BATH, AND W.I.C, LAUNDRY ROOM
- Permit Issued
- Issued on 1/3/2023
- Issuing Office
- Current Status
- Issued on 1/3/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | NGHI SU |
| Corrections Issued | 11/15/2022 | NGHI SU |
| Quality Review Completed | 11/23/2022 | FARUK SEZER |
| Applicant returned to address corrections | 12/16/2022 | NGHI SU |
| Plan Check Approved | 12/28/2022 | NGHI SU |
| Issued | 1/3/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/6/2022 | CINDY QI |
| Sewer availability | Cleared | 12/6/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Kunyoung; Lic. No.: C66880 | 22812 ERIEL AVE TORRANCE, CA 90505 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/10/2023 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 4/3/2023 | Approved | SABAS ALONSO |
| Insulation | 4/18/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 4/18/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 5/17/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 5/17/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/17/2023 | Approved | SABAS ALONSO |
| Insulation | 5/24/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/30/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/5/2023 | Partial Approval | BRENDAN MORELLI |
| Shower Pan | 6/5/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 6/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/13/2023 | Approved | SABAS ALONSO |
| Final | 8/17/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/17/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 8/17/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 10/16/2023 | Approved | ANTHONY EGSON |
| Final | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 10/16/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 10/16/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | ANTHONY EGSON |
| Special/Order Compliance | 11/13/2023 | Corrections Issued | ANTHONY EGSON |