3430 W CASITAS AVE 90039
Certificate Information: 3430 W CASITAS AVE 90039
- Application / Permit
- 22014-10000-05191
- Plan Check / Job No.
- B22LA21208
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage into ADU with addition per Ordinance LAMC 12.22 A.33 (c) and (e)
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2022 | VICTOR CHEN |
| Corrections Issued | 10/27/2022 | VICTOR CHEN |
| Building Plans Picked Up | 10/31/2022 | APPLICANT |
| Applicant returned to address corrections | 11/15/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/2/2022 | MINA HABILI |
| Plan Check Approved | 1/12/2023 | FERNANDO FLORES |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 3/19/2024 | HAMIK HARTOUNIAN |
| No Progress | 3/29/2024 | CHARLES BOGHOSKHAN |
| No Progress | 3/29/2024 | CHARLES BOGHOSKHAN |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 11/1/2022 | DANG NGUYEN |
| Address approval | Cleared | 11/3/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 11/9/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/1/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Sewer | 3/8/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/8/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/9/2023 | Approved | HAMIK HARTOUNIAN |
| Sewer | 4/7/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 4/21/2023 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/25/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/4/2023 | Partial Inspection | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 5/11/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/26/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/26/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 6/26/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/6/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/6/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 7/6/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/6/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/6/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/11/2023 | Approved | RUBEN SALAS |
| Drywall Nailing | 7/27/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/27/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 7/27/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/23/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 10/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 10/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 10/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 10/23/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/23/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 12/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 12/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 12/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 3/18/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 3/18/2024 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 3/18/2024 | Approved | HAMIK HARTOUNIAN |