4926 S 7TH AVE 90043
Certificate Information: 4926 S 7TH AVE 90043
- Application / Permit
- 22014-10000-05177
- Plan Check / Job No.
- B22LA21176
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. (N) DETACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 4/2/2023
- Issuing Office
- Current Status
- CofO Issued on 9/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2022 | ZAW HAN |
| Corrections Issued | 10/26/2022 | ZAW HAN |
| Applicant returned to address corrections | 12/8/2022 | ZAW HAN |
| Plan Check Approved | 12/25/2022 | KHUONG TRUONG |
| Plan Check Approved | 12/25/2022 | FERNANDO FLORES |
| Issued | 4/2/2023 | APPLICANT |
| CofO in Progress | 9/15/2025 | LUIS CASTRO |
| CofO in Progress | 9/16/2025 | LUIS CASTRO |
| Permit Finaled | 9/21/2025 | DEROLD HAUFF |
| CofO Issued | 9/21/2025 | DEROLD HAUFF |
| Permit Finaled | 9/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 12/5/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 12/21/2022 | STEVE MELGAR |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Bell Construction West; Lic. No.: 853579-B | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 6/1/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 6/12/2023 | Corrections Issued | ANTHONY EGSON |
| Pre-Inspection | 6/12/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 6/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 6/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 6/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 6/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Pre-Inspection | 10/30/2023 | No Access for Inspection | ANTHONY EGSON |
| Sewer | 11/2/2023 | Corrections Issued | ANTHONY EGSON |
| Sewer | 11/6/2023 | No Access for Inspection | ANTHONY EGSON |
| Sewer | 11/20/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 6/28/2024 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 9/23/2024 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 10/3/2024 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 10/7/2024 | No Access for Inspection | AMIR NAZARIAN |
| Pre-Inspection | 10/9/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 10/11/2024 | No Access for Inspection | ANTHONY EGSON |
| HVAC-Rough | 10/16/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 10/17/2024 | No Access for Inspection | ANTHONY EGSON |
| Pre-Inspection | 10/23/2024 | Approved | BARRY HACHE |
| Pre-Inspection | 11/5/2024 | Corrections Issued | BARRY HACHE |
| Pre-Inspection | 11/8/2024 | Approved | BARRY HACHE |
| Pre-Inspection | 11/14/2024 | Corrections Issued | MICHAEL LEWIS |
| Deputy Wood Construction | 12/4/2024 | Conditional Approval | BARRY HACHE |
| Wood Frame | 12/10/2024 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 1/3/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 1/3/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 1/3/2025 | Approved | LUIS CASTRO |
| Underground Mechanical | 1/3/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/17/2025 | Conditional Approval | MICHAEL LEWIS |
| HVAC-Rough | 1/17/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 1/17/2025 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/28/2025 | Partial Approval | ANTHONY RAMOS |
| Insulation | 2/13/2025 | Partial Approval | LUIS CASTRO |
| Drywall Nailing | 2/24/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 2/24/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 4/29/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 5/28/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 5/28/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 6/5/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 6/5/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 6/5/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | LUIS CASTRO |
| Final | 8/29/2025 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 8/29/2025 | Approved | LUIS CASTRO |
| Green Building Final | 8/29/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | LUIS CASTRO |
| Service/Power Release | 8/29/2025 | Conditional Approval | LUIS CASTRO |
| Smoke Detectors | 8/29/2025 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 8/29/2025 | Approved | LUIS CASTRO |
| Final | 9/9/2025 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 9/9/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 9/12/2025 | OK to Issue CofO | LUIS CASTRO |
| Service/Power Release | 9/12/2025 | Approved | LUIS CASTRO |
| Final | 9/15/2025 | OK to Issue CofO | LUIS CASTRO |