2600 W 74TH ST 90043
Certificate Information: 2600 W 74TH ST 90043
- Application / Permit
- 22014-10000-05176
- Plan Check / Job No.
- B22LA21174
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION OF 500 SQ FT TO (E) SFD (1-STORY)
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | CARLOS MONTES |
| Corrections Issued | 10/31/2022 | CARLOS MONTES |
| Quality Review Completed | 11/16/2022 | KEN GILL |
| Building Plans Picked Up | 11/28/2022 | APPLICANT |
| Applicant returned to address corrections | 2/24/2023 | CARLOS MONTES |
| Plan Check Approved | 4/19/2023 | CARLOS MONTES |
| Issued | 4/21/2023 | APPLICANT |
| CofO in Progress | 1/8/2024 | ENRIQUE MIRELES |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
| CofO Issued | 1/13/2024 | DEROLD HAUFF |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2022 | CINDY QI |
| Sewer availability | Cleared | 12/19/2022 | CINDY QI |
| Low Impact Development | Cleared | 4/6/2023 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 4/11/2023 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/18/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 6/6/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 6/6/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 6/12/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/7/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/7/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/7/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/7/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/7/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 8/7/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 8/14/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/18/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/30/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 8/30/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 10/30/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/2/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 11/2/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 11/2/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/2/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 11/2/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/21/2023 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 11/21/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 11/21/2023 | Approved | ENRIQUE MIRELES |
| Final | 12/22/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 1/4/2024 | OK to Issue CofO | ENRIQUE MIRELES |