2600 W 74TH ST 90043

Certificate Information: 2600 W 74TH ST 90043

Application / Permit
22014-10000-05176
Plan Check / Job No.
B22LA21174
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION OF 500 SQ FT TO (E) SFD (1-STORY)
Permit Issued
Issued on 4/21/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 CARLOS MONTES
Corrections Issued 10/31/2022 CARLOS MONTES
Quality Review Completed 11/16/2022 KEN GILL
Building Plans Picked Up 11/28/2022 APPLICANT
Applicant returned to address corrections 2/24/2023 CARLOS MONTES
Plan Check Approved 4/19/2023 CARLOS MONTES
Issued 4/21/2023 APPLICANT
CofO in Progress 1/8/2024 ENRIQUE MIRELES
Permit Finaled 1/13/2024 DEROLD HAUFF
CofO Issued 1/13/2024 DEROLD HAUFF
Permit Finaled 1/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/19/2022 CINDY QI
Sewer availability Cleared 12/19/2022 CINDY QI
Low Impact Development Cleared 4/6/2023 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 4/11/2023 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/18/2023 Approved ENRIQUE MIRELES
Underground Mechanical 6/6/2023 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 6/6/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Approved ENRIQUE MIRELES
Insulation 6/12/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/7/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/7/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Approved ENRIQUE MIRELES
Green Building Rough 8/7/2023 Approved ENRIQUE MIRELES
HVAC-Rough 8/7/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/7/2023 Approved ENRIQUE MIRELES
Sewer 8/7/2023 Approved ENRIQUE MIRELES
Insulation 8/14/2023 Approved ENRIQUE MIRELES
Drywall Nailing 8/18/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/30/2023 Approved ENRIQUE MIRELES
Shower Pan 8/30/2023 Approved ENRIQUE MIRELES
Service/Power Release 10/30/2023 Approved ENRIQUE MIRELES
Final 11/2/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 11/2/2023 Approved ENRIQUE MIRELES
Green Building Final 11/2/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 11/2/2023 Approved ENRIQUE MIRELES
Underground Mechanical 11/2/2023 Approved ENRIQUE MIRELES
Final 11/21/2023 Corrections Issued ENRIQUE MIRELES
Gas Test 11/21/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 11/21/2023 Approved ENRIQUE MIRELES
Final 12/22/2023 Corrections Issued ENRIQUE MIRELES
Final 1/4/2024 OK to Issue CofO ENRIQUE MIRELES