950 N CHATTANOOGA AVE 90272

Certificate Information: 950 N CHATTANOOGA AVE 90272

Application / Permit
22014-10000-05173
Plan Check / Job No.
B22LA21163
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 2nd story to (E) SFD with deck - total 1,774 SF Interior & exterior remodel of the first floor of (E) SFD New driveway, landscape, plantings, hardscapes
Permit Issued
Issued on 8/9/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 NGHI SU
Corrections Issued 10/28/2022 NGHI SU
Quality Review Completed 10/28/2022 FARUK SEZER
Building Plans Picked Up 10/31/2022 APPLICANT
Plan Check Approved 6/5/2023 NGHI SU
Issued 8/9/2023 APPLICANT
Permit Finaled 2/24/2026 CLAUDIO MORENO
CofO Issued 2/24/2026 CLAUDIO MORENO
Permit Finaled 2/24/2026 CLAUDIO MORENO

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/5/2022 SAUL GARCIA
BHO/Hillside ordinance Cleared 11/5/2022 SAUL GARCIA
BHO/Hillside ordinance Cleared 11/5/2022 SAUL GARCIA
BHO/Hillside ordinance Cleared 11/5/2022 SAUL GARCIA
Permit Cleared 11/5/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 1/4/2023 SAUL GARCIA
Sewer availability Cleared 1/4/2023 SAUL GARCIA
Hydrant and Access approval Cleared 1/9/2023 KURT CORRAL
Trees in Parkway Cleared 1/10/2023 ADALBERTO VERA
Coastal Zone Cleared 1/30/2023 RUBEN VASQUEZ
Miscellaneous Cleared 1/30/2023 RUBEN VASQUEZ
ZI Cleared 1/30/2023 RUBEN VASQUEZ
BHO/Hillside ordinance Cleared 4/11/2023 JASON NG
GPI Written Notices Cleared 4/14/2023 NGHI SU
Low Impact Development Cleared 5/15/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/16/2023 JASON NG
Grading Pre-Inspection Cleared 6/5/2023 NGHI SU

Contact Information

Architect Hefner,, William Robert; Lic. No.: C17013 5820 WILSHIRE BLVD SUITE 500      LOS ANGELES, CA 90036
Contractor Kavin Fence And Construction Company; Lic. No.: 356032-B 3814 WILLAT AVENUE      CULVER CITY, CA 90232
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Galbreath,, Sean; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106
Engineer Gotsis,, Jason James; Lic. No.: C65701 429 REED COURT      GOLETA, CA 93117
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 10/11/2023 Approved RYAN BARNES
Sewer 10/23/2023 Partial Approval RYAN BARNES
Excavation/Setback/Form/Re-Bar 11/7/2023 Approved RYAN BARNES
Deputy Drilled-In Anchors 11/30/2023 Approved RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Approved ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Approval RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Conditional Approval RYAN BARNES
HVAC-Rough 3/27/2024 Approved JOHN MATTILLO
ELECTRICAL-Rough 3/29/2024 Approved ANDREW BEELI
Gas Test 3/29/2024 Approved ANDREW BEELI
PLUMBING-Rough 3/29/2024 Approved ANDREW BEELI
BUILDING-Rough-Frame 4/29/2024 Conditional Approval RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Conditional Approval RYAN BARNES
Green Building Rough 4/29/2024 Approved RYAN BARNES
Verify Sprinkler Sign Off 4/29/2024 Not Ready for Inspection RYAN BARNES
Interior/Exterior Lathing 5/10/2024 Partial Approval RYAN BARNES
Insulation 6/5/2024 Conditional Approval RYAN BARNES
Drywall Nailing 6/21/2024 Approved RYAN BARNES
Shower Pan 6/26/2024 Approved RYAN BARNES
Interior/Exterior Lathing 7/11/2024 Approved JOHN MATTILLO
Masonry Wall/Backfill 8/8/2024 Not Ready for Inspection ANDREW BEELI
SUSMP-Std. Urban Storm Water 8/8/2024 Partial Approval ANDREW BEELI
Masonry Wall/Backfill 8/15/2024 Not Ready for Inspection RYAN BARNES
Underground Mechanical 8/15/2024 Partial Approval RYAN BARNES
Masonry Wall/Backfill 8/29/2024 Approved RYAN BARNES
Excavation/Setback/Form/Re-Bar 9/18/2024 Partial Approval RYAN BARNES
Excavation/Setback/Form/Re-Bar 9/23/2024 Partial Approval RYAN BARNES
Service/Power Release 12/26/2024 Approved JOHN MATTILLO
Pre-Inspection 5/28/2025 Approved RYAN BARNES
ELECTRICAL-Final 6/10/2025 No Access for Inspection RYAN BARNES
PLUMBING-Final 6/10/2025 No Access for Inspection RYAN BARNES
ELECTRICAL-Final 6/11/2025 Corrections Issued RYAN BARNES
PLUMBING-Final 6/11/2025 Approved RYAN BARNES
BUILDING-Rough-Frame 2/12/2026 Approved RYAN BARNES
Final 2/12/2026 Conditional Approval RYAN BARNES
Footing/Foundation/Slab 2/12/2026 Approved RYAN BARNES
Green Building Final 2/12/2026 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Approved RYAN BARNES
Smoke Detectors 2/12/2026 Approved RYAN BARNES
Verify Sprinkler Sign Off 2/12/2026 Approved RYAN BARNES