6506 W 87TH PL 90045
Certificate Information: 6506 W 87TH PL 90045
- Application / Permit
- 22014-10000-05160
- Plan Check / Job No.
- B22LA21104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD bathroom and interiro remodel to the (e) sfd.
- Permit Issued
- Issued on 12/2/2022
- Issuing Office
- Current Status
- CofO Issued on 5/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | JOE VO |
| Corrections Issued | 10/21/2022 | JOE VO |
| Plan Check Approved | 11/3/2022 | JOE VO |
| Issued | 12/2/2022 | APPLICANT |
| CofO in Progress | 5/9/2023 | BOBBY KEY |
| Permit Finaled | 5/11/2023 | DANIEL ORRANTE |
| CofO Issued | 5/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/25/2022 | JENSON LEE |
| Sewer availability | Cleared | 10/25/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | JENSON LEE |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/12/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 12/13/2022 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 12/13/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 12/19/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 1/3/2023 | Partial Approval | BOBBY KEY |
| Wood Frame | 1/3/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/23/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/28/2023 | Approved | EVAN COOPER |
| Green Building Rough | 2/28/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 2/28/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/28/2023 | Partial Approval | EVAN COOPER |
| Wood Frame | 2/28/2023 | Approved | EVAN COOPER |
| Insulation | 3/3/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/8/2023 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 3/24/2023 | Approved | BOBBY KEY |
| Shower Pan | 3/24/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 5/9/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/9/2023 | Approved | BOBBY KEY |
| Final | 5/9/2023 | OK to Issue CofO | BOBBY KEY |
| Footing/Foundation/Slab | 5/9/2023 | Approved | BOBBY KEY |
| HVAC-Final | 5/9/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/9/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/9/2023 | Approved | BOBBY KEY |