7640 N OSTROM AVE 91406

Certificate Information: 7640 N OSTROM AVE 91406

Application / Permit
22014-10000-05143
Plan Check / Job No.
B22LA20953
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 20'-0" x 18-0" GARAGE WITH (N) 18'-0" x 13'-6" ADDITION INTO A (N) DETACHED IRREGULAR SHAPED 38'-0" x 18'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 5/8/2023
Issuing Office
Current Status
CofO Issued on 7/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 LAWRENCE QUIRANTE
Corrections Issued 10/22/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 10/27/2022 APPLICANT
Applicant returned to address corrections 1/11/2023 MINA HABILI
Applicant returned to address corrections 2/2/2023 VICTOR CHEN
Plan Check Approved 5/8/2023 ALFRED RAMIREZ
Issued 5/8/2023 APPLICANT
CofO in Progress 6/20/2024 RAUL OLAGI
Permit Finaled 7/8/2024 RUBEN SALAS
CofO Issued 7/8/2024 RUBEN SALAS
Permit Finaled 7/8/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/20/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 12/20/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 1/9/2023 MEGAN GODINEZ
Sewer availability Cleared 1/9/2023 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 1/9/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 1/9/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 1/9/2023 MEGAN GODINEZ
Construction near power lines Cleared 5/5/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/26/2023 Approved RAUL OLAGI
PLUMBING-Rough 10/26/2023 Partial Approval RAUL OLAGI
Sewer 10/26/2023 Approved RAUL OLAGI
Underground Mechanical 1/5/2024 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 1/10/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval RAUL OLAGI
Underground Mechanical 1/18/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/8/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/8/2024 Corrections Issued RAUL OLAGI
Green Building Rough 2/8/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 2/8/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/12/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/12/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved RAUL OLAGI
PLUMBING-Rough 2/12/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/27/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 2/27/2024 Approved RAUL OLAGI
HVAC-Rough 2/27/2024 Approved RAUL OLAGI
Insulation 2/29/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 2/29/2024 Partial Approval RAUL OLAGI
Drywall Nailing 3/6/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 3/8/2024 Approved SALVADOR MARTINEZ
Final 6/6/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 6/11/2024 Approved RAUL OLAGI
ELECTRICAL-Final 6/11/2024 Corrections Issued RAUL OLAGI
Final 6/11/2024 Corrections Issued RAUL OLAGI
Green Building Rough 6/11/2024 Approved RAUL OLAGI
HVAC-Final 6/11/2024 Corrections Issued RAUL OLAGI
PLUMBING-Final 6/11/2024 Corrections Issued RAUL OLAGI
Smoke Detectors 6/11/2024 Approved RAUL OLAGI
Final 6/18/2024 OK to Issue CofO RAUL OLAGI
Green Building Final 6/18/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Approved RAUL OLAGI
Service/Power Release 6/18/2024 Approved RAUL OLAGI