4050 N VERDUGO ROAD 90065

Certificate Information: 4050 N VERDUGO ROAD 90065

Application / Permit
22014-10000-05138
Plan Check / Job No.
B22LA20926
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Addition and change of use from used car sales to retail.
Permit Issued
Issued on 8/5/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 ERIC WONG
Corrections Issued 10/22/2022 ERIC WONG
Green Plans Picked Up 11/1/2022 APPLICANT
Quality Review Completed 11/2/2022 KEN GILL
Building Plans Picked Up 11/30/2022 APPLICANT
Applicant returned to address corrections 12/2/2022 ERIC WONG
Plan Check Approved 12/22/2022 ERIC WONG
Issued 8/5/2024 APPLICANT
CofO in Progress 4/8/2025 RONALD JIMENEZ
CofO Issued 4/8/2025 ERNESTO CORRAL
Permit Finaled 4/8/2025 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 11/3/2022 SHASHA YU
Roof/Waste drainage to street Cleared 11/5/2022 ADRIAN SANCHEZ
Sewer availability Cleared 11/5/2022 ADRIAN SANCHEZ
Supp. Use District POD/CDO/TDO Cleared 11/21/2022 NASHYA JENSEN
ZI Cleared 11/21/2022 NASHYA JENSEN
Eng Process Fee Ord 176,300 Cleared 11/29/2022 ADRIAN SANCHEZ
DAS Clearance Cleared 12/7/2022 ERIC WONG
Green Code Cleared 12/15/2022 AARON COSTA
Grading Pre-Inspection Cleared 12/22/2022 ERIC WONG

Contact Information

Contractor Fine Lifestyle Construction Inc; Lic. No.: 1006760-B 14431 VENTURA BLVD SUITE 402      SHERMAN OAKS, CA 91423
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/17/2024 Not Ready for Inspection PAUL BAZERKANIAN
Footing/Foundation/Slab 9/19/2024 Approved RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Partial Approval PAUL BAZERKANIAN
Green Building Rough 11/1/2024 Not Ready for Inspection JEROME BLACKWOOD
Interior/Exterior Lathing 11/5/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Rough 12/19/2024 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 12/19/2024 Approved RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 1/3/2025 Approved RAMAZANALI ALMASI
Green Building Rough 1/16/2025 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 1/16/2025 Conditional Approval RAMAZANALI ALMASI
Insulation 1/22/2025 Approved RAMAZANALI ALMASI
Drywall Nailing 1/27/2025 Approved RAMAZANALI ALMASI
Special/Order Compliance 1/29/2025 Approved RAFAEL CORTES
Final 4/7/2025 OK to Issue CofO RONALD JIMENEZ
Green Building Final 4/7/2025 Approved RONALD JIMENEZ
Green Building Rough 4/7/2025 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Gas Company RONALD JIMENEZ
Smoke Detectors 4/7/2025 Approved RONALD JIMENEZ
Wood Frame 4/7/2025 Approved RONALD JIMENEZ