2547 S GREENFIELD AVE 90064

Certificate Information: 2547 S GREENFIELD AVE 90064

Application / Permit
22014-10000-05136
Plan Check / Job No.
B22LA20912
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN* 15'-5" X 14'-0" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING - ALL WORK PER ENGINEER
Permit Issued
Issued on 1/9/2023
Issuing Office
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/21/2022 DANIEL ABRAMYAN
Corrections Issued 10/24/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 11/22/2022 DANIEL ABRAMYAN
Plan Check Approved 12/15/2022 ANDREW SANTIAGO
Issued 1/9/2023 APPLICANT
Permit Finaled 6/23/2025 RICHARD STEINBACH
CofO Issued 6/23/2025 RICHARD STEINBACH
Permit Finaled 6/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2022 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 12/6/2022 ANTHONY MAINEZ
Specific Plan Cleared 12/6/2022 KYLE WINSTON
Grading Pre-Inspection Cleared 12/9/2022 ALEXANDER HELFER
Specific Plan Cleared 12/14/2022 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Martinez,, Michael Anthony; Lic. No.: S3825 902 15TH PLACE      HERMOSA BEACH, CA 90254

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Conditional Approval CLAYTON GRAHAM
Underground Mechanical 3/13/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 4/21/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 4/21/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval EVAN COOPER
Green Building Rough 4/21/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/21/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 5/1/2023 Approved JOHNNY MIRANDA
Green Building Rough 5/1/2023 Approved JOHNNY MIRANDA
HVAC-Rough 5/1/2023 Approved JOHNNY MIRANDA
Insulation 5/1/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/1/2023 Partial Approval JOHNNY MIRANDA
Drywall Nailing 5/8/2023 Approved MICHAEL PELHAM
Interior/Exterior Lathing 5/8/2023 Approved MICHAEL PELHAM
Final 6/2/2023 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 6/2/2023 Approved JOHNNY MIRANDA
Green Building Final 6/2/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 6/2/2023 Approved JOHNNY MIRANDA
Final 6/8/2023 Conditional Approval JESUS PINEDA