613 S WESTHOLME AVE 90024
Certificate Information: 613 S WESTHOLME AVE 90024
- Application / Permit
- 22014-10000-05109
- Plan Check / Job No.
- B22LA20831
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert Existing 1-STORY GARAGE TO RECREATION ROOM AT FIRST FLOOR AND ADU AT SECOND FLOOR. RECREATION ROOM (255 SF) AND ADU (302 F)
- Permit Issued
- Issued on 3/10/2024
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 11/17/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/28/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/1/2023 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/21/2023 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/11/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/26/2023 | CRYSTEL MAALOUF |
| Issued | 3/10/2024 | APPLICANT |
| CofO in Progress | 3/5/2025 | STEPHANIE SWANSON |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2023 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/27/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | DINAH GARIN |
| Sewer availability | Cleared | 8/1/2023 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 8/14/2023 | SERGIO VALENZUELA |
| Specific Plan | Cleared | 8/15/2023 | EDUARDO HERMOSO |
| GPI Written Notices | Cleared | 10/13/2023 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Bahman Keyvani; Lic. No.: 923783-B | , |
| Contractor | Keyvani Bahman; Lic. No.: 923783-B | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/30/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/7/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/7/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 7/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/7/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 8/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/8/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/15/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 10/15/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/15/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 10/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 10/25/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 11/5/2024 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 11/7/2024 | Approved | REGINA MENDEZ |
| Insulation | 11/7/2024 | Approved | REGINA MENDEZ |
| Shower Pan | 11/7/2024 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 11/19/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 2/4/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 2/4/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 2/4/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 2/4/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 2/4/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 2/25/2025 | Approved | STEPHANIE SWANSON |
| Final | 2/25/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 2/25/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 2/25/2025 | Approved | STEPHANIE SWANSON |
| Final | 3/5/2025 | OK to Issue CofO | STEPHANIE SWANSON |