730 W 56TH ST 90037

Certificate Information: 730 W 56TH ST 90037

Application / Permit
22014-10000-05087
Plan Check / Job No.
B22LA20756
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY BEDROOM ADDITION AT REAR OF (E) SFD.
Permit Issued
Issued on 3/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 LAWRENCE QUIRANTE
Corrections Issued 10/20/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 12/16/2022 APPLICANT
Plan Check Approved 3/28/2023 ZAW HAN
Issued 3/28/2023 APPLICANT
CofO in Progress 7/30/2024 SABAS ALONSO
CofO Issued 8/5/2024 DEROLD HAUFF
Permit Finaled 8/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 1/24/2023 AMAAN MALIK
Sewer availability Cleared 1/24/2023 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/11/2023 Corrections Issued SABAS ALONSO
Pre-Inspection 5/11/2023 Partial Inspection SABAS ALONSO
Wood Frame 5/11/2023 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 6/6/2023 Corrections Issued SCOTT FINNILA
Pre-Inspection 6/6/2023 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 6/29/2023 Corrections Issued SABAS ALONSO
Pre-Inspection 6/29/2023 Partial Inspection SABAS ALONSO
Pre-Inspection 9/18/2023 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/7/2023 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 2/9/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 3/1/2024 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 3/1/2024 Corrections Issued ANTHONY EGSON
Insulation 3/1/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 3/1/2024 Not Ready for Inspection ANTHONY EGSON
Wood Frame 3/1/2024 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 3/15/2024 Corrections Issued DAVID FEILER
Insulation 3/15/2024 Not Ready for Inspection DAVID FEILER
Wood Frame 3/15/2024 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/22/2024 Approved SABAS ALONSO
Insulation 3/22/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 3/22/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/18/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 4/18/2024 Approved SABAS ALONSO
Green Building Rough 4/18/2024 Approved SABAS ALONSO
HVAC-Rough 4/18/2024 Approved SABAS ALONSO
PLUMBING-Rough 4/18/2024 Approved SABAS ALONSO
Insulation 4/25/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Approved BRENDAN MORELLI
Drywall Nailing 6/17/2024 Approved SABAS ALONSO
Final 6/17/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 6/17/2024 Approved SABAS ALONSO
Green Building Final 6/17/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 6/17/2024 Corrections Issued SABAS ALONSO
Final 7/29/2024 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 7/29/2024 Approved SABAS ALONSO