806-808 S VALITA ST 90291

Certificate Information: 806-808 S VALITA ST 90291

Application / Permit
22014-10000-05066
Plan Check / Job No.
B22LA20681
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NFPA 13D FIRE SPRINKLERS REQUIRED. MAJOR REMODEL AND NEW 1ST AND 2ND FLOOR ADDITION TO AN EXISTING SINGLE FAMILY DWELLING. NEW ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 12/5/2022
Issuing Office
Current Status
CofO Issued on 1/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 KEVIN MORALES
Corrections Issued 10/18/2022 KEVIN MORALES
Quality Review Completed 10/18/2022 EUGENE BARBEAU
Applicant returned to address corrections 11/9/2022 KEVIN MORALES
Plan Check Approved 12/5/2022 KEVIN MORALES
Issued 12/5/2022 APPLICANT
CofO in Progress 1/11/2024 HERBERT GIRON
Permit Finaled 1/12/2024 DANIEL ORRANTE
CofO Issued 1/12/2024 DANIEL ORRANTE
Permit Finaled 1/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/17/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/17/2022 DINAH GARIN
Permit Cleared 10/17/2022 DINAH GARIN
Sewer availability Cleared 10/17/2022 DINAH GARIN
Trees in Parkway Cleared 11/3/2022 ADALBERTO VERA
Low Impact Development Cleared 11/4/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 11/5/2022 STEVEN JIN
Specific Plan Cleared 11/17/2022 FREDDY GARCIA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: NA23971       ,
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B       ,
Engineer Nguyen,, Huan; Lic. No.: NA64238       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/22/2023 Partial Approval EVAN COOPER
Sewer 5/30/2023 Approved EVAN COOPER
Underground Mechanical 5/30/2023 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/8/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 6/8/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 6/16/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval EVAN COOPER
Underground Mechanical 7/24/2023 Partial Approval EVAN COOPER
Deputy Wood Construction 7/26/2023 Conditional Approval EVAN COOPER
PLUMBING-Rough 7/26/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/31/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 8/3/2023 Approved EVAN COOPER
HVAC-Rough 8/7/2023 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 8/10/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved EVAN COOPER
Interior/Exterior Lathing 8/10/2023 Partial Approval EVAN COOPER
Shower Pan 8/10/2023 Approved EVAN COOPER
Insulation 8/21/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 8/21/2023 Approved BEN MOLSTAD
Drywall Nailing 8/28/2023 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 8/28/2023 Approved TEMISTOCLES CAAL
Underground Mechanical 9/14/2023 Partial Approval HERBERT GIRON
Underground Mechanical 9/18/2023 Approved HERBERT GIRON
ELECTRICAL-Final 11/6/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 11/8/2023 Corrections Issued HERBERT GIRON
Gas Test 11/8/2023 Approved HERBERT GIRON
PLUMBING-Final 11/8/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved HERBERT GIRON
HVAC-Final 11/15/2023 Corrections Issued HERBERT GIRON
Final 11/30/2023 Corrections Issued HERBERT GIRON
HVAC-Final 11/30/2023 Approved HERBERT GIRON
Smoke Detectors 11/30/2023 Approved HERBERT GIRON
ELECTRICAL-Final 1/10/2024 Approved HERBERT GIRON
Final 1/10/2024 OK to Issue CofO HERBERT GIRON
Service/Power Release 1/10/2024 Approved HERBERT GIRON