806-808 S VALITA ST 90291
Certificate Information: 806-808 S VALITA ST 90291
- Application / Permit
- 22014-10000-05066
- Plan Check / Job No.
- B22LA20681
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. NFPA 13D FIRE SPRINKLERS REQUIRED. MAJOR REMODEL AND NEW 1ST AND 2ND FLOOR ADDITION TO AN EXISTING SINGLE FAMILY DWELLING. NEW ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | KEVIN MORALES |
| Corrections Issued | 10/18/2022 | KEVIN MORALES |
| Quality Review Completed | 10/18/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/9/2022 | KEVIN MORALES |
| Plan Check Approved | 12/5/2022 | KEVIN MORALES |
| Issued | 12/5/2022 | APPLICANT |
| CofO in Progress | 1/11/2024 | HERBERT GIRON |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
| CofO Issued | 1/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | DINAH GARIN |
| Permit | Cleared | 10/17/2022 | DINAH GARIN |
| Sewer availability | Cleared | 10/17/2022 | DINAH GARIN |
| Trees in Parkway | Cleared | 11/3/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 11/4/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 11/5/2022 | STEVEN JIN |
| Specific Plan | Cleared | 11/17/2022 | FREDDY GARCIA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | , |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/22/2023 | Partial Approval | EVAN COOPER |
| Sewer | 5/30/2023 | Approved | EVAN COOPER |
| Underground Mechanical | 5/30/2023 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/8/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 6/8/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 6/16/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 7/24/2023 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 7/26/2023 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 7/26/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 7/31/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/3/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 8/7/2023 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | EVAN COOPER |
| Shower Pan | 8/10/2023 | Approved | EVAN COOPER |
| Insulation | 8/21/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/21/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 8/28/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/28/2023 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 9/14/2023 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 9/18/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/6/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 11/8/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 11/8/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/8/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | HERBERT GIRON |
| HVAC-Final | 11/15/2023 | Corrections Issued | HERBERT GIRON |
| Final | 11/30/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/30/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 11/30/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 1/10/2024 | Approved | HERBERT GIRON |
| Final | 1/10/2024 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 1/10/2024 | Approved | HERBERT GIRON |