4135 W 59TH PL 90043
Certificate Information: 4135 W 59TH PL 90043
- Application / Permit
- 22014-10000-05048
- Plan Check / Job No.
- B22LA20598
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 9'-11" X 11'-2" PORTION OF (E) DETACHED GARAGE TO STORAGE WITH REMAINING PORTION OF DETACHED GARAGE CONVERTED INTO (N) ACCESSORY DWELLING UNIT WITH 14'-4" X 16'-0" IRREGULAR SHAPED ADDITION PER LAMC 12.22.A.33 (c) AND (d) AND 14'-4" X 7'-0" ATTACHED PATIO COVER.
- Permit Issued
- Issued on 9/19/2024
- Issuing Office
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 10/21/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 7/15/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 9/4/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 9/5/2024 | SERGIO MUNIZ |
| Plan Check Approved | 9/11/2024 | JEROME MAGAT PALMA |
| Issued | 9/19/2024 | APPLICANT |
| CofO in Progress | 4/7/2026 | SALVADOR MARTINEZ |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
| CofO Issued | 4/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | NEIL TUANO |
| Sewer availability | Cleared | 8/1/2023 | NEIL TUANO |
| Abandoned oil well | Cleared | 1/12/2024 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 2/22/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 7/19/2024 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 9/4/2024 | ALEC MOUSAKHANIAN |
Contact Information
| Contractor | A D A Construction; Lic. No.: 693982-B | , |
| Contractor | Anderson Heritage Builders; Lic. No.: 693982-B | , |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Corrections Issued | WAYNE REGESTER |
| Pre-Inspection | 5/6/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 7/2/2025 | Partial Approval | WAYNE REGESTER |
| Underground Mechanical | 7/2/2025 | Approved | WAYNE REGESTER |
| Footing/Foundation/Slab | 7/11/2025 | Not Ready for Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/1/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/15/2025 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 10/15/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/15/2025 | Approved | SALVADOR MARTINEZ |
| Sewer | 10/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 10/15/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/20/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 10/20/2025 | Approved | BRENDAN MORELLI |
| Service/Power Release | 10/20/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Sewer | 10/20/2025 | Approved | BRENDAN MORELLI |
| Service/Power Release | 10/27/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Shower Pan | 10/27/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 11/4/2025 | Partial Approval | SALVADOR MARTINEZ |
| Shower Pan | 11/4/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/10/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 11/10/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 11/19/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 12/5/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 12/15/2025 | Approved | DEVON JACKSON |
| ELECTRICAL-Final | 3/16/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 3/16/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 3/16/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 3/16/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 3/16/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 3/16/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 3/23/2026 | Approved | SALVADOR MARTINEZ |
| Final | 3/23/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Gas Test | 3/23/2026 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 3/23/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 3/23/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 3/23/2026 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 3/26/2026 | Approved | SALVADOR MARTINEZ |
| Final | 3/26/2026 | OK to Issue CofO | SALVADOR MARTINEZ |
| HVAC-Final | 3/26/2026 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 3/26/2026 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 3/26/2026 | Approved | SALVADOR MARTINEZ |