2752 S THURMAN AVE 90016
Certificate Information: 2752 S THURMAN AVE 90016
- Application / Permit
- 22014-10000-05045
- Plan Check / Job No.
- B22LA20595
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION (97 SF) OF (E) DEATCHED 2-CAR GARAGE TO ADU PER LAMC 12.22A.33(c)-(e).
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Current Status
- Issued on 1/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2022 | VIVIAN LAO |
| Corrections Issued | 10/19/2022 | VIVIAN LAO |
| Plan Check Approved | 1/16/2023 | HERNAN ARREOLA |
| Issued | 1/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 11/1/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 12/28/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/12/2023 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: NA53284 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/21/2023 | Conditional Approval | JOSE AVILA |
| METHANE-Subgrade | 7/21/2023 | Corrections Issued | JOSE AVILA |
| Sewer | 7/21/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/21/2023 | Approved | LILIANA PORTILLO |
| METHANE-Barrier | 11/21/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 11/21/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 3/6/2024 | Approved | STUART CHAPMAN |
| HVAC-Rough | 3/6/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/6/2024 | Approved | STUART CHAPMAN |
| Insulation | 4/11/2024 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | RICHARD DOCKUS |
| Drywall Nailing | 4/16/2024 | Approved | RICHARD DOCKUS |
| Green Building Rough | 4/16/2024 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/2/2024 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 8/13/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 11/14/2024 | Approved | LUIS CASTRO |
| Final | 11/14/2024 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 11/14/2024 | Approved | LUIS CASTRO |
| METHANE-Final | 11/14/2024 | Approved | LUIS CASTRO |
| METHANE-Rough | 11/14/2024 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 11/14/2024 | Approved | LUIS CASTRO |
| Final | 11/21/2024 | Partial Approval | ARTHUR NEGRETE |
| Final | 12/6/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 1/2/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 1/2/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 1/2/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 1/2/2025 | Approved | ARTHUR NEGRETE |