2664 S VETERAN AVE 90064

Certificate Information: 2664 S VETERAN AVE 90064

Application / Permit
22014-10000-05032
Plan Check / Job No.
B22LA20493
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan - CONVERT EXISTING DETACHED 2-CAR GARAGE TO AN ADU AND ADDITION TO ADU. PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/9/2022
Issuing Office
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2022 APPLICANT
Assigned to Plan Check Engineer 10/17/2022 ALFREDO JARA
Corrections Issued 10/19/2022 ALFREDO JARA
Plan Check Approved 11/9/2022 ALFREDO JARA
Issued 11/9/2022 APPLICANT
CofO in Progress 12/4/2023 JESUS PINEDA
CofO in Progress 12/4/2023 JESUS PINEDA
Permit Finaled 12/7/2023 DANIEL ORRANTE
CofO Issued 12/7/2023 DANIEL ORRANTE
Permit Finaled 12/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/22/2022 STEVEN JIN
Roof/Waste drainage to street Cleared 10/22/2022 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 11/2/2022 JENSON LEE
Sewer availability Cleared 11/2/2022 JENSON LEE
Grading Pre-Inspection Cleared 11/9/2022 ALFREDO JARA

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/8/2023 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 3/8/2023 Not Ready for Inspection JOHNNY MIRANDA
Sewer 3/8/2023 Conditional Approval JOHNNY MIRANDA
Underground Mechanical 3/8/2023 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 3/10/2023 Partial Approval JOHNNY MIRANDA
Sewer 3/10/2023 Approved JOHNNY MIRANDA
Underground Mechanical 3/10/2023 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
MERV13>=Rough 4/5/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/21/2023 Corrections Issued EVAN COOPER
HVAC-Rough 4/21/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 4/21/2023 Approved EVAN COOPER
ELECTRICAL-Rough 4/26/2023 Approved HERBERT GIRON
HVAC-Rough 4/26/2023 Approved HERBERT GIRON
Shower Pan 4/26/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 No Access for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 5/3/2023 Not Ready for Inspection JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Approved JEREMY TODD
MERV13>=Rough 5/3/2023 Approved JEREMY TODD
Insulation 5/9/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/9/2023 Approved JOHNNY MIRANDA
Drywall Nailing 5/18/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 8/8/2023 Approved JESUS PINEDA
ELECTRICAL-Final 8/8/2023 Approved JESUS PINEDA
Final 8/8/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 8/8/2023 Approved JESUS PINEDA
HVAC-Final 8/8/2023 Corrections Issued JESUS PINEDA
MERV13>=Final 8/8/2023 Approved JESUS PINEDA
MERV13>=Rough 8/8/2023 Approved JESUS PINEDA
PLUMBING-Final 8/8/2023 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Not Ready JESUS PINEDA
Service/Power Release 8/8/2023 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 8/8/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Not Ready JESUS PINEDA
Final 8/24/2023 Not Ready for Inspection JESUS PINEDA
Final 10/10/2023 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 10/10/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Approved JESUS PINEDA
Final 12/4/2023 OK to Issue CofO JESUS PINEDA