1949 N COLDWATER CANYON DR 90210
Certificate Information: 1949 N COLDWATER CANYON DR 90210
- Application / Permit
- 22014-10000-05029
- Plan Check / Job No.
- B22LA20492
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: ADDING 162.62 SQ.FT. IN FIRST FLOOR ADDING 1,743.4 SQ.FT. IN SECOND FLOOR ADDING 36.66 COVER PORCH
- Permit Issued
- Issued on 3/2/2023
- Issuing Office
- Current Status
- CofO Issued on 11/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 11/17/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/21/2022 | GARO TELMI |
| Plan Check Approved | 2/16/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/2/2023 | INTERNET PERMIT |
| Issued | 3/2/2023 | APPLICANT |
| CofO in Progress | 11/13/2023 | STUART CHAPMAN |
| Permit Finaled | 11/15/2023 | DEROLD HAUFF |
| CofO Issued | 11/15/2023 | DEROLD HAUFF |
| Permit Finaled | 11/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/31/2022 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | JENSON LEE |
| Sewer availability | Cleared | 12/12/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 12/13/2022 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 12/20/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 12/23/2022 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 12/23/2022 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 12/23/2022 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 12/23/2022 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 12/23/2022 | RAYMOND MUGAMBWA |
| GPI Written Notices | Cleared | 2/16/2023 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: NA82330 | , |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 3/9/2023 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/9/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/29/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 3/29/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 3/29/2023 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Partial Approval | RAUL BARAJAS |
| Insulation | 4/3/2023 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/10/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Conditional Approval | RAUL BARAJAS |
| Green Building Rough | 5/10/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Wood Construction | 5/17/2023 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/9/2023 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 6/9/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 6/9/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 6/13/2023 | Approved | RAUL BARAJAS |
| Insulation | 6/22/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/22/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 6/22/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 7/6/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 7/6/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 7/6/2023 | Approved | RAUL BARAJAS |
| Service/Power Release | 7/27/2023 | Corrections Issued | RAUL BARAJAS |
| Service/Power Release | 8/3/2023 | Partial Approval | RAUL BARAJAS |
| Service/Power Release | 9/6/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/24/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 10/24/2023 | Approved | BRIAN SULLIVAN |
| Final | 10/24/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 10/24/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 10/24/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 10/24/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 10/24/2023 | Approved | BRIAN SULLIVAN |
| Final | 11/9/2023 | OK to Issue CofO | STUART CHAPMAN |