1170-1172 S LUCERNE BLVD 90019
Certificate Information: 1170-1172 S LUCERNE BLVD 90019
- Application / Permit
- 22014-10000-05027
- Plan Check / Job No.
- B22LA20490
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan -PROPOSED 2-STORY ADDITION TO SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, NEW RECROOM AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ; NFPA-13D FIRE SPRINKLER IS REQUIRED
- Permit Issued
- Issued on 7/11/2023
- Issuing Office
- Current Status
- CofO Issued on 4/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | SINA KHOSRAVI |
| Corrections Issued | 11/4/2022 | SINA KHOSRAVI |
| Quality Review Completed | 11/10/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 2/1/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/6/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/23/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/3/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/9/2023 | SINA KHOSRAVI |
| Plan Check Approved | 3/16/2023 | SINA KHOSRAVI |
| Plan Check Approved | 6/2/2023 | SINA KHOSRAVI |
| Issued | 7/11/2023 | APPLICANT |
| CofO in Progress | 3/25/2026 | JUSTIN HAWLEY |
| CofO in Progress | 3/26/2026 | JUSTIN HAWLEY |
| CofO in Progress | 3/31/2026 | JUSTIN HAWLEY |
| Permit Finaled | 4/1/2026 | DEROLD HAUFF |
| CofO Issued | 4/1/2026 | DEROLD HAUFF |
| Permit Finaled | 4/1/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2022 | TREVOR QUAN |
| Permit | Cleared | 12/8/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 12/12/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 12/13/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 1/31/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/9/2023 | TREVOR QUAN |
Contact Information
| Contractor | M General Construction The; Lic. No.: 1055278-B | , |
| Engineer | Rasheed,, Zoher Elhashmi; Lic. No.: C58615 | 641 GALLOPING COALT CIR WALNUT, CA 91789 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Barrier | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/2/2023 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 11/2/2023 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 11/2/2023 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/27/2023 | No Access for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/19/2024 | Partial Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/21/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/26/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Partial Approval | JUSTIN HAWLEY |
| Special/Order Compliance | 5/3/2024 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/17/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Corrections Issued | JUSTIN HAWLEY |
| Gas Test | 1/17/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 1/17/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/22/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 1/22/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 1/22/2025 | Corrections Issued | JUSTIN HAWLEY |
| Deputy Wood Construction | 2/18/2025 | Conditional Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 2/18/2025 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/27/2025 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/27/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 3/10/2025 | Corrections Issued | JEFFREY MEAD |
| Insulation | 3/27/2025 | Conditional Approval | ALEX COLIN |
| Drywall Nailing | 4/7/2025 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 4/15/2025 | Partial Approval | JOSH MEISTER |
| Interior/Exterior Lathing | 4/15/2025 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | JUSTIN HAWLEY |
| Final | 8/15/2025 | Corrections Issued | JUSTIN HAWLEY |
| METHANE-Final | 8/15/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Not Ready | JUSTIN HAWLEY |
| Service/Power Release | 11/7/2025 | Corrections Issued | MICHAEL LEWIS |
| Service/Power Release | 11/14/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | JUSTIN HAWLEY |
| Drywall Nailing | 3/25/2026 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/25/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/25/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 3/25/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/25/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 3/25/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/31/2026 | OK to Issue CofO | JUSTIN HAWLEY |