1170-1172 S LUCERNE BLVD 90019

Certificate Information: 1170-1172 S LUCERNE BLVD 90019

Application / Permit
22014-10000-05027
Plan Check / Job No.
B22LA20490
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan -PROPOSED 2-STORY ADDITION TO SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, NEW RECROOM AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ; NFPA-13D FIRE SPRINKLER IS REQUIRED
Permit Issued
Issued on 7/11/2023
Issuing Office
Current Status
CofO Issued on 4/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 SINA KHOSRAVI
Corrections Issued 11/4/2022 SINA KHOSRAVI
Quality Review Completed 11/10/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 2/1/2023 SINA KHOSRAVI
Applicant returned to address corrections 2/6/2023 SINA KHOSRAVI
Applicant returned to address corrections 2/23/2023 SINA KHOSRAVI
Applicant returned to address corrections 3/3/2023 SINA KHOSRAVI
Applicant returned to address corrections 3/9/2023 SINA KHOSRAVI
Plan Check Approved 3/16/2023 SINA KHOSRAVI
Plan Check Approved 6/2/2023 SINA KHOSRAVI
Issued 7/11/2023 APPLICANT
CofO in Progress 3/25/2026 JUSTIN HAWLEY
CofO in Progress 3/26/2026 JUSTIN HAWLEY
CofO in Progress 3/31/2026 JUSTIN HAWLEY
Permit Finaled 4/1/2026 DEROLD HAUFF
CofO Issued 4/1/2026 DEROLD HAUFF
Permit Finaled 4/1/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/17/2022 TREVOR QUAN
Permit Cleared 12/8/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/12/2022 TREVOR QUAN
Sewer availability Cleared 12/12/2022 TREVOR QUAN
Hydrant and Access approval Cleared 12/13/2022 KURT CORRAL
Low Impact Development Cleared 1/31/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/9/2023 TREVOR QUAN

Contact Information

Contractor M General Construction The; Lic. No.: 1055278-B       ,
Engineer Rasheed,, Zoher Elhashmi; Lic. No.: C58615 641 GALLOPING COALT CIR      WALNUT, CA 91789

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/12/2023 Corrections Issued JOAQUIN GREENOUGH
METHANE-Barrier 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/2/2023 Corrections Issued STUART CHAPMAN
METHANE-Barrier 11/2/2023 Approved STUART CHAPMAN
METHANE-Subgrade 11/2/2023 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 11/27/2023 No Access for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 3/19/2024 Partial Approval JUSTIN HAWLEY
Footing/Foundation/Slab 3/21/2024 Approved STUART CHAPMAN
PLUMBING-Rough 4/26/2024 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval JUSTIN HAWLEY
Special/Order Compliance 5/3/2024 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Corrections Issued JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 1/17/2025 Corrections Issued JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Corrections Issued JUSTIN HAWLEY
Gas Test 1/17/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 1/17/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 1/22/2025 Not Ready for Inspection JUSTIN HAWLEY
Gas Test 1/22/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 1/22/2025 Corrections Issued JUSTIN HAWLEY
Deputy Wood Construction 2/18/2025 Conditional Approval NICHOLAS LOPEZ
PLUMBING-Rough 2/18/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/27/2025 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 2/27/2025 Approved ENRIQUE MIRELES
Insulation 3/10/2025 Corrections Issued JEFFREY MEAD
Insulation 3/27/2025 Conditional Approval ALEX COLIN
Drywall Nailing 4/7/2025 Corrections Issued RONNIE MINDANAO
Drywall Nailing 4/15/2025 Partial Approval JOSH MEISTER
Interior/Exterior Lathing 4/15/2025 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 8/15/2025 Approved JUSTIN HAWLEY
Final 8/15/2025 Corrections Issued JUSTIN HAWLEY
METHANE-Final 8/15/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Not Ready JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 11/7/2025 Corrections Issued MICHAEL LEWIS
Service/Power Release 11/14/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready JUSTIN HAWLEY
Drywall Nailing 3/25/2026 Approved JUSTIN HAWLEY
ELECTRICAL-Final 3/25/2026 Approved JUSTIN HAWLEY
Final 3/25/2026 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Final 3/25/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 3/25/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 3/25/2026 Approved JUSTIN HAWLEY
Final 3/31/2026 OK to Issue CofO JUSTIN HAWLEY