18646 W BRYANT ST 91324
Certificate Information: 18646 W BRYANT ST 91324
- Application / Permit
- 22014-10000-05020
- Plan Check / Job No.
- B22LA20468
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2) Major Remodel and 393 SF addition to the rear of (E) SFD. Building shall be fully sprinklered.
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Current Status
- CofO Issued on 8/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2022 | WEIJIAN HUANG |
| Corrections Issued | 10/19/2022 | WEIJIAN HUANG |
| Building Plans Picked Up | 10/24/2022 | APPLICANT |
| Applicant returned to address corrections | 1/10/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 1/13/2023 | MOHAMMAD ESMAILI |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 8/18/2023 | JOHN KIDWELL |
| Permit Finaled | 8/18/2023 | DANIEL ORRANTE |
| CofO Issued | 8/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/9/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 1/3/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/4/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/18/2023 | Partial Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/18/2023 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 1/18/2023 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 1/18/2023 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 1/24/2023 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 1/24/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/23/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/23/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 2/23/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/3/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 3/3/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/3/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Shower Pan | 3/3/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/10/2023 | Partial Approval | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 3/10/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/24/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/24/2023 | Approved | DAVID SCANTLIN |
| Insulation | 3/24/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 3/24/2023 | Partial Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 3/28/2023 | Approved | JOHN KIDWELL |
| Underground Mechanical | 4/4/2023 | Approved | DAVID SCANTLIN |
| Final | 5/9/2023 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/9/2023 | Approved | JOHN KIDWELL |
| Green Building Final | 5/9/2023 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 5/9/2023 | Approved | JOHN KIDWELL |
| Final | 8/17/2023 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 8/17/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Approved | JOHN KIDWELL |