11956 W ANETA ST 90230

Certificate Information: 11956 W ANETA ST 90230

Application / Permit
22014-10000-05019
Plan Check / Job No.
B22LA20467
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NFPA13D FIRE SPRINKLERS REQUIRED. MAJOR REMODEL AND NEW ADDITION TO (E) SINGLE FAMILY DWELLING WITH AN ATTACHED CARPORT.
Permit Issued
Issued on 1/9/2024
Issuing Office
Current Status
CofO Issued on 10/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 KEVIN MORALES
Corrections Issued 10/18/2022 KEVIN MORALES
Quality Review Completed 10/18/2022 EUGENE BARBEAU
Building Plans Picked Up 10/21/2022 APPLICANT
Plan Check Approved 1/9/2024 KEVIN MORALES
Issued 1/9/2024 APPLICANT
CofO in Progress 10/17/2025 RUBEN RIVAS
Permit Finaled 10/21/2025 RICHARD STEINBACH
CofO Issued 10/21/2025 RICHARD STEINBACH
Permit Finaled 10/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 2/23/2023 FREDDY GARCIA
Low Impact Development Cleared 12/1/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/10/2023 AHMED AMARRAGY
Sewer availability Cleared 12/17/2023 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 1/9/2024 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/24/2024 No Access for Inspection TEMISTOCLES CAAL
Pre-Inspection 7/9/2024 Partial Inspection BOBBY KEY
Deputy Drilled-In Anchors 7/15/2024 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 7/19/2024 Corrections Issued BOBBY KEY
Excavation/Setback/Form/Re-Bar 7/23/2024 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 7/30/2024 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 8/12/2024 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 8/26/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 9/16/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 10/11/2024 Corrections Issued TEMISTOCLES CAAL
Deputy Reinf. Concrete 10/18/2024 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 10/23/2024 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 10/23/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 10/23/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 10/29/2024 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 10/29/2024 Conditional Approval MICHAEL ALLEN
Green Building Rough 10/29/2024 Partial Approval MICHAEL ALLEN
HVAC-Rough 10/29/2024 Approved MICHAEL ALLEN
Shower Pan 10/31/2024 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 11/4/2024 Corrections Issued HERBERT GIRON
Green Building Rough 11/4/2024 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 11/4/2024 Partial Approval HERBERT GIRON
Special/Order Compliance 11/4/2024 Partial Inspection TEMISTOCLES CAAL
Verify Sprinkler Sign Off 11/4/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 11/15/2024 Approved REGINA MENDEZ
BUILDING-Rough-Frame 11/21/2024 Corrections Issued MICHAEL ALLEN
Insulation 11/21/2024 Approved MICHAEL ALLEN
Wood Frame 11/25/2024 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 12/2/2024 Partial Approval MICHAEL ALLEN
Drywall Nailing 12/2/2024 Approved MICHAEL ALLEN
Green Building Rough 12/2/2024 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 12/30/2024 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Not Ready RUBEN RIVAS
Final 6/27/2025 Not Ready for Inspection RUBEN RIVAS
Footing/Foundation/Slab 6/27/2025 Approved RUBEN RIVAS
Green Building Final 6/27/2025 Approved RUBEN RIVAS
MERV13>=Final 6/27/2025 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Required RUBEN RIVAS
Smoke Detectors 6/27/2025 Approved RUBEN RIVAS
Final 7/21/2025 Corrections Issued RUBEN RIVAS
Final 10/10/2025 OK to Issue CofO RUBEN RIVAS
Service/Power Release 10/10/2025 Approved RUBEN RIVAS