11956 W ANETA ST 90230
Certificate Information: 11956 W ANETA ST 90230
- Application / Permit
- 22014-10000-05019
- Plan Check / Job No.
- B22LA20467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NFPA13D FIRE SPRINKLERS REQUIRED. MAJOR REMODEL AND NEW ADDITION TO (E) SINGLE FAMILY DWELLING WITH AN ATTACHED CARPORT.
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Current Status
- CofO Issued on 10/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | KEVIN MORALES |
| Corrections Issued | 10/18/2022 | KEVIN MORALES |
| Quality Review Completed | 10/18/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 10/21/2022 | APPLICANT |
| Plan Check Approved | 1/9/2024 | KEVIN MORALES |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 10/17/2025 | RUBEN RIVAS |
| Permit Finaled | 10/21/2025 | RICHARD STEINBACH |
| CofO Issued | 10/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/23/2023 | FREDDY GARCIA |
| Low Impact Development | Cleared | 12/1/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 12/10/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 12/17/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2024 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| Pre-Inspection | 7/9/2024 | Partial Inspection | BOBBY KEY |
| Deputy Drilled-In Anchors | 7/15/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/19/2024 | Corrections Issued | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 7/30/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 8/12/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 8/26/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/16/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 10/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 10/18/2024 | Conditional Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 10/23/2024 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 10/23/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/23/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/29/2024 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 10/29/2024 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 10/29/2024 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 10/29/2024 | Approved | MICHAEL ALLEN |
| Shower Pan | 10/31/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/4/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 11/4/2024 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 11/4/2024 | Partial Approval | HERBERT GIRON |
| Special/Order Compliance | 11/4/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 11/4/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/15/2024 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 11/21/2024 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 11/21/2024 | Approved | MICHAEL ALLEN |
| Wood Frame | 11/25/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/2/2024 | Partial Approval | MICHAEL ALLEN |
| Drywall Nailing | 12/2/2024 | Approved | MICHAEL ALLEN |
| Green Building Rough | 12/2/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Not Ready | RUBEN RIVAS |
| Final | 6/27/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Footing/Foundation/Slab | 6/27/2025 | Approved | RUBEN RIVAS |
| Green Building Final | 6/27/2025 | Approved | RUBEN RIVAS |
| MERV13>=Final | 6/27/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Required | RUBEN RIVAS |
| Smoke Detectors | 6/27/2025 | Approved | RUBEN RIVAS |
| Final | 7/21/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 10/10/2025 | OK to Issue CofO | RUBEN RIVAS |
| Service/Power Release | 10/10/2025 | Approved | RUBEN RIVAS |