2412 S DUXBURY PL 90034
Certificate Information: 2412 S DUXBURY PL 90034
- Application / Permit
- 22014-10000-05008
- Plan Check / Job No.
- B22LA20391
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and 35 sf addition
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Current Status
- CofO Issued on 5/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2022 | JOE VO |
| Corrections Issued | 10/13/2022 | JOE VO |
| Plan Check Approved | 12/8/2022 | JOE VO |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 5/3/2023 | CLAYTON GRAHAM |
| Permit Finaled | 5/4/2023 | DANIEL ORRANTE |
| CofO Issued | 5/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/13/2022 | MANUEL TEJADA |
| Roof/Waste drainage to street | Cleared | 11/28/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | CATHERINE ADROVER |
Contact Information
| Contractor | Quality First Builders Inc; Lic. No.: 990316-B | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/13/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/13/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| METHANE-Barrier | 1/13/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 1/13/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/31/2023 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Barrier | 1/31/2023 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 1/31/2023 | Approved | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 2/2/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/15/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 2/15/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 2/15/2023 | Approved | ASHLEY THOMPSON |
| Rough-Elec/Plmb/HVAC | 2/15/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 2/24/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/24/2023 | Approved | ASHLEY THOMPSON |
| Insulation | 2/28/2023 | No Access for Inspection | DAVID FEILER |
| Insulation | 3/1/2023 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 3/2/2023 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 3/2/2023 | Approved | ASHLEY THOMPSON |
| Final | 4/25/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 4/25/2023 | Approved | CLAYTON GRAHAM |
| Smoke Detectors | 4/25/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Final | 4/28/2023 | Approved | CLAYTON GRAHAM |
| Final | 4/28/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| Green Building Final | 4/28/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 4/28/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 4/28/2023 | Approved | CLAYTON GRAHAM |
| Smoke Detectors | 4/28/2023 | Approved | CLAYTON GRAHAM |