9111 W CRESTA DR 90035
Certificate Information: 9111 W CRESTA DR 90035
- Application / Permit
- 22014-10000-05005
- Plan Check / Job No.
- B22LA20388
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Addition and remodel to an existing single-story SDF, patio with trellis, and adding a new second story. 2 car garage addition. NFPA-13D Fire Sprinkler system is required.
- Permit Issued
- Issued on 11/17/2023
- Issuing Office
- Current Status
- Issued on 11/17/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | NGHI SU |
| Corrections Issued | 10/29/2022 | NGHI SU |
| Quality Review Completed | 11/1/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/11/2023 | NGHI SU |
| Applicant returned to address corrections | 10/19/2023 | NGHI SU |
| Plan Check Approved | 11/16/2023 | NGHI SU |
| Issued | 11/17/2023 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/23/2023 | KENTON TRINH |
| Trees in Parkway | Cleared | 5/11/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/27/2023 | MELINEH AGHAKHABIAN |
| Permit | Cleared | 10/30/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 10/30/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/31/2023 | DARIN LAM |
| GPI Written Notices | Cleared | 11/6/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 11/6/2023 | NGHI SU |
Contact Information
| Architect | Heifetz,, Daniel Eli; Lic. No.: C30912 | HEIFETZ ARCHITECTS 22701 WEST MARTHA STREET WOODLAND HILLS, CA 91367 |
| Contractor | Builders & Son'S Inc; Lic. No.: 961171-B | , |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Barrier | 1/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Subgrade | 1/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/30/2024 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 1/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 1/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Pre-Inspection | 1/31/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 2/1/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 7/24/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 7/24/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/26/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2024 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 7/26/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 7/26/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 7/29/2024 | Partial Approval | REGINA MENDEZ |
| BUILDING-Rough-Frame | 8/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 8/5/2024 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 8/5/2024 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/5/2024 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Rough | 8/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 8/5/2024 | Partial Inspection | REGINA MENDEZ |
| BUILDING-Rough-Frame | 8/14/2024 | Conditional Approval | ASHLEY THOMPSON |
| METHANE-Rough | 8/14/2024 | Corrections Issued | ASHLEY THOMPSON |
| Shower Pan | 8/14/2024 | Approved | ASHLEY THOMPSON |
| Insulation | 8/19/2024 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 8/26/2024 | Corrections Issued | REGINA MENDEZ |
| Drywall Nailing | 8/26/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 8/27/2024 | Approved | REGINA MENDEZ |
| Drywall Nailing | 8/27/2024 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/30/2024 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 12/5/2025 | Partial Approval | ASHLEY THOMPSON |
| Final | 12/5/2025 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 12/5/2025 | Approved | ASHLEY THOMPSON |
| Green Building Final | 12/5/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 12/5/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Final | 12/5/2025 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Rough | 12/5/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 12/5/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 12/5/2025 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 12/5/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/13/2026 | Conditional Approval | ASHLEY THOMPSON |
| Final | 5/13/2026 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Final | 5/13/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 5/13/2026 | Approved | ASHLEY THOMPSON |