204 W 107TH ST 90003
Certificate Information: 204 W 107TH ST 90003
- Application / Permit
- 22014-10000-05004
- Plan Check / Job No.
- B22LA20386
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: REMOVE 3'-0" x 17'-0" PORTION OF (E) DETACHED GARAGE AND CONVERT THE (E) DETACHED GARAGE WITH A 15'-0" x 18'-0" ADDITION TO BE A (N) DETACHED IRREGULAR SHAPED 20'-0" x 31'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 3/11/2023
- Issuing Office
- Current Status
- CofO Issued on 4/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2022 | ALFRED RAMIREZ |
| Corrections Issued | 10/18/2022 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 2/17/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/3/2023 | ALEC MOUSAKHANIAN |
| Issued | 3/11/2023 | APPLICANT |
| CofO in Progress | 4/24/2024 | JAMES CHAVEZ |
| CofO Issued | 4/25/2024 | ANSON MAGLASANG |
| Permit Finaled | 4/25/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 10/28/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | CELINA MORENO |
| Sewer availability | Cleared | 11/28/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 4/5/2023 | No Access for Inspection | JAMES CHAVEZ |
| Underground Mechanical | 4/7/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 4/27/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 7/25/2023 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 8/2/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 8/15/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/25/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| Insulation | 9/1/2023 | Approved | JOHN KLARIN |
| Shower Pan | 9/1/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 9/18/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/6/2023 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Final | 1/19/2024 | Corrections Issued | JOHN KLARIN |
| Gas Test | 1/19/2024 | Approved | JOHN KLARIN |
| Green Building Final | 1/19/2024 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 1/19/2024 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 1/19/2024 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Not Ready | JOHN KLARIN |
| Final | 3/13/2024 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 3/13/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/13/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 3/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 3/29/2024 | Partial Approval | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 3/29/2024 | Approved | BEN MOLSTAD |
| Final | 4/1/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 4/19/2024 | Conditional Approval | JAMES CHAVEZ |
| Final | 4/24/2024 | OK to Issue CofO | JAMES CHAVEZ |