2723 S RIMPAU BLVD 90016
Certificate Information: 2723 S RIMPAU BLVD 90016
- Application / Permit
- 22014-10000-04988
- Plan Check / Job No.
- B22LA20356
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERSION OF (E) GARAGE WITH ATT. REC ROOM TO ADU WITH NEW ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/15/2024
- Issuing Office
- Current Status
- CofO Issued on 3/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 11/16/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/23/2022 | GARO TELMI |
| Plan Check Approved | 7/9/2024 | MAHNAZ NOURHASHEMI |
| Issued | 7/15/2024 | APPLICANT |
| CofO in Progress | 3/11/2025 | JOSE MACIAS |
| No Progress | 3/16/2025 | DEROLD HAUFF |
| CofO in Progress | 3/16/2025 | DEROLD HAUFF |
| CofO Issued | 3/26/2025 | DEROLD HAUFF |
| Permit Finaled | 3/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | WALLIE JONG |
| Sewer availability | Cleared | 3/9/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/24/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 8/15/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 8/19/2023 | MSTAFA AL-MSARI |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 8/19/2024 | Approved | JUSTIN HAWLEY |
| Sewer | 8/19/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 8/19/2024 | Approved | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 8/29/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 8/30/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 9/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 9/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 9/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 9/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Deputy Drilled-In Anchors | 9/18/2024 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/19/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/19/2024 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 9/19/2024 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/19/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/19/2024 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 9/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/30/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 9/30/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 9/30/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/30/2024 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 10/2/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/2/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 10/7/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/28/2024 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 10/30/2024 | Approved | ANTHONY RAMOS |
| Final | 3/5/2025 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 3/5/2025 | Approved | JEFFREY MEAD |
| Final | 3/10/2025 | OK to Issue CofO | JOSE MACIAS |