3543 S BUTLER AVE 90066

Certificate Information: 3543 S BUTLER AVE 90066

Application / Permit
22014-10000-04957
Plan Check / Job No.
B22LA20249
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: Str. Remodel to (E) att. Garage and New 2nd story ADU addition above, per LAMC 12.22 A.33 to an (E) 2-Story SFD with (N) Patio Cover
Permit Issued
Issued on 4/4/2023
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 MAHNAZ NOURHASHEMI
Corrections Issued 11/4/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 11/15/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 1/17/2023 MAHNAZ NOURHASHEMI
Issued 4/4/2023 APPLICANT
CofO in Progress 10/2/2025 KIRK SANDERS
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/21/2022 SAUL GARCIA
Specific Plan Cleared 11/21/2022 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 11/22/2022 SAUL GARCIA
Grading Pre-Inspection Cleared 11/22/2022 KIRK LINKLATER
Sewer availability Cleared 11/22/2022 SAUL GARCIA
Low Impact Development Cleared 1/12/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 1/12/2023 SAUL GARCIA
GPI Written Notices Cleared 4/3/2023 MAHNAZ NOURHASHEMI

Contact Information

Contractor A B Construction; Lic. No.: 936625-B 12010 SYLVESTER STREET      LOS ANGELES, CA 90066
Engineer Paniagua,, Cristobal; Lic. No.: C72894 1538 W 92ND ST      LOS ANGELES, CA 90047

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/2/2023 Approved JOHNNY MIRANDA
Deputy Reinf. Concrete 5/5/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 8/18/2023 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Not Ready for Inspection JESUS PINEDA
Special/Order Compliance 8/22/2023 Partial Inspection BEN MOLSTAD
ELECTRICAL-Rough 9/7/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval JESUS PINEDA
HVAC-Rough 9/7/2023 Approved JESUS PINEDA
PLUMBING-Rough 9/7/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 9/29/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 10/3/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 10/26/2023 Partial Inspection JESUS PINEDA
Special/Order Compliance 10/26/2023 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 11/13/2023 Approved JESUS PINEDA
Insulation 11/13/2023 Corrections Issued JESUS PINEDA
Insulation 11/21/2023 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 11/21/2023 Partial Approval TEMISTOCLES CAAL
Drywall Nailing 11/30/2023 Approved KENNETH NAGLE
Shower Pan 2/1/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 2/14/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 3/27/2025 Corrections Issued WILBER ROSALES
HVAC-Final 3/27/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 3/27/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Final 4/10/2025 Approved WILBER ROSALES
Final 4/10/2025 Corrections Issued WILBER ROSALES
HVAC-Final 4/10/2025 Approved WILBER ROSALES
PLUMBING-Final 4/10/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Not Ready WILBER ROSALES
Smoke Detectors 4/10/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Approved WILBER ROSALES
Final 10/1/2025 OK to Issue CofO KIRK SANDERS
Service/Power Release 10/1/2025 Approved KIRK SANDERS