24714 3/4 S AVALON BLVD 90744
Certificate Information: 24714 3/4 S AVALON BLVD 90744
- Application / Permit
- 22014-10000-04949
- Plan Check / Job No.
- B22LA20214
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERET (4) CAR GARAGES INTO TWO ADU'S PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A33(c)(d)(g)
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 5/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | KHUONG TRUONG |
| Corrections Issued | 10/8/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 10/26/2022 | APPLICANT |
| Applicant returned to address corrections | 10/19/2023 | RICARDO RAMIREZ |
| Issued | 10/26/2023 | APPLICANT |
| CofO in Progress | 5/1/2025 | EUGENE CASSIDY |
| CofO Issued | 5/1/2025 | ANSON MAGLASANG |
| Permit Finaled | 5/1/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2022 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | ANA SORIANO |
| Sewer availability | Cleared | 12/27/2022 | ANA SORIANO |
| "Q" conditions | Cleared | 6/9/2023 | DANIEL CORONADO |
| Low Impact Development | Cleared | 10/9/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 10/16/2023 | KHAING AYE |
Contact Information
| Contractor | Nunez General Contractors Inc; Lic. No.: 912178-B | P O BOX 1079 SOUTH GATE, CA 90280 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 6/24/2024 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 6/24/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/5/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/5/2024 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 7/5/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/5/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/15/2024 | Approved | EUGENE CASSIDY |
| Final | 10/31/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/31/2024 | Approved | EUGENE CASSIDY |
| Green Building Final | 10/31/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 10/31/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 10/31/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/31/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 10/31/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 10/31/2024 | Approved | EUGENE CASSIDY |
| Final | 4/9/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/9/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | EUGENE CASSIDY |
| Final | 4/30/2025 | OK to Issue CofO | EUGENE CASSIDY |