10570 W LE CONTE AVE 90024
Certificate Information: 10570 W LE CONTE AVE 90024
- Application / Permit
- 22014-10000-04946
- Plan Check / Job No.
- B22LA20206
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: LAUNDRY ROOM ADDITION TO (E) SFD
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | KHUONG TRUONG |
| Corrections Issued | 10/14/2022 | KHUONG TRUONG |
| Plan Check Approved | 10/31/2022 | KHUONG TRUONG |
| Issued | 11/2/2022 | APPLICANT |
| CofO in Progress | 10/13/2023 | STEPHANIE SWANSON |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/22/2022 | STEVEN JIN |
| Sewer availability | Cleared | 10/22/2022 | STEVEN JIN |
| Grading Pre-Inspection | Cleared | 10/25/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2022 | DINAH GARIN |
Contact Information
| Architect | Spock,, Karen Zindler- Shuler; Lic. No.: NA25136 | , |
| Contractor | Scheer Construction Inc; Lic. No.: 697213-B | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/25/2023 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 3/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/1/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/7/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/7/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/21/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/29/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/12/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/12/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 4/12/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/17/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 4/17/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 4/17/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/8/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | CHRISTOPHER WILSON |
| Final | 8/21/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/21/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 8/21/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 8/21/2023 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 8/21/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 9/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 9/28/2023 | Approved | STEPHANIE SWANSON |
| Smoke Detectors | 9/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 10/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| Smoke Detectors | 10/10/2023 | Approved | STEPHANIE SWANSON |
| Final | 10/12/2023 | Partial Approval | STEPHANIE SWANSON |
| Final | 10/13/2023 | OK to Issue CofO | STEPHANIE SWANSON |