12416 W SARAH ST 91604
Certificate Information: 12416 W SARAH ST 91604
- Application / Permit
- 22014-10000-04923
- Plan Check / Job No.
- B22LA18194
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPlan. SECOND STORY ADDITION TO EXISTING GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/7/2025
- Issuing Office
- Current Status
- Issued on 2/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | MONICA RAMIREZ |
| Corrections Issued | 10/5/2022 | MONICA RAMIREZ |
| Quality Review Completed | 10/6/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/8/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/13/2023 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/19/2023 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/31/2023 | MONICA RAMIREZ |
| Applicant returned to address corrections | 4/25/2023 | MONICA RAMIREZ |
| Plan Check Approved | 4/26/2023 | MONICA RAMIREZ |
| Issued | 2/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2022 | RYAN KIM |
| Sewer availability | Cleared | 10/13/2022 | RYAN KIM |
| ZI | Cleared | 10/24/2022 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 11/14/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/4/2023 | RYAN KIM |
Contact Information
| Architect | , ; Lic. No.: C40202 | , |
| Contractor | Owner-Builder | , |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 2/28/2025 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 3/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 3/12/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 3/12/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 3/14/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/19/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 3/19/2025 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/21/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 4/4/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/7/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/7/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 4/10/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 4/14/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/11/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/6/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/6/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Final | 1/6/2026 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/6/2026 | Approved | CHRISTOPHE COCHRAN |