12021 W DEWEY ST 90066
Certificate Information: 12021 W DEWEY ST 90066
- Application / Permit
- 22014-10000-04893
- Plan Check / Job No.
- B22LA19918
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Conversion of Existing Garage into ADU and addition
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Current Status
- CofO Issued on 8/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2022 | RICARDO RAMIREZ |
| Corrections Issued | 10/13/2022 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/22/2022 | FERNANDO FLORES |
| Plan Check Approved | 1/12/2023 | ARSALAN SHABESTARI |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 7/31/2023 | JESUS PINEDA |
| Permit Finaled | 8/3/2023 | DANIEL ORRANTE |
| CofO Issued | 8/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2022 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 11/1/2022 | AHMED AMARRAGY |
| Grading Pre-Inspection | Cleared | 11/17/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 11/17/2022 | VALERIA CEJA |
| Roof/Waste drainage to street | Cleared | 11/28/2022 | AHMED AMARRAGY |
| Construction near power lines | Cleared | 1/8/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/8/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Ram Construction & Electrical; Lic. No.: 1064340-B | , |
| Contractor | The Contractor Gal; Lic. No.: 1064340-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/1/2023 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/7/2023 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 2/7/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/2/2023 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/2/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 3/2/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/2/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/9/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/9/2023 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 3/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 3/16/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 3/16/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 3/17/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 3/17/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 3/20/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/29/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Not Ready | JESUS PINEDA |
| Final | 7/13/2023 | Corrections Issued | DAVID FEILER |
| Green Building Final | 7/13/2023 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 7/13/2023 | Approved | DAVID FEILER |
| Final | 7/28/2023 | OK to Issue CofO | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | JESUS PINEDA |