5250 W 8TH ST 90036

Certificate Information: 5250 W 8TH ST 90036

Application / Permit
22014-10000-04883
Plan Check / Job No.
B22LA13847
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
REMODEL EXISTING 2 STORY ATTACHED ACCESSORY STRUCTURE TO COMPLY WITH WORK UNDER 22014-10000-03564 TO BECOME A DETACHED ACCESSORY BUILDING
Permit Issued
Issued on 2/13/2023
Issuing Office
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 GEORGE ALVAREZ
Corrections Issued 7/25/2022 GEORGE ALVAREZ
Applicant returned to address corrections 9/19/2022 GEORGE ALVAREZ
Applicant returned to address corrections 10/3/2022 ADAM HEGAZI
Plan Check Approved 10/18/2022 JOSEPH RAFOLS
Issued 2/13/2023 APPLICANT
CofO in Progress 10/28/2024 JOAQUIN GREENOUGH
Permit Finaled 11/1/2024 DEROLD HAUFF
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Lcp General Construction Inc; Lic. No.: 1031198-B       ,
Engineer Yiu,, Siu Fung; Lic. No.: S5801 PO BOX 5143      EL MONTE, CA 91734

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/5/2023 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 6/21/2023 Corrections Issued RICHARD DOCKUS
Deputy Reinf. Concrete 6/23/2023 Conditional Approval RICHARD DOCKUS
Footing/Foundation/Slab 7/7/2023 Approved RICHARD DOCKUS
METHANE-Barrier 7/7/2023 Approved RICHARD DOCKUS
METHANE-Subgrade 7/7/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 7/7/2023 Partial Approval RICHARD DOCKUS
Deputy Reinf. Concrete 7/17/2023 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 10/31/2023 Approved RICHARD DOCKUS
Green Building Rough 10/31/2023 Approved RICHARD DOCKUS
METHANE-Rough 10/31/2023 Approved RICHARD DOCKUS
Wood Frame 11/1/2023 Approved RICHARD DOCKUS
Final 10/18/2024 Corrections Issued JOAQUIN GREENOUGH
Final 10/18/2024 Partial Inspection JOAQUIN GREENOUGH
Green Building Final 10/18/2024 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 10/18/2024 Approved JOAQUIN GREENOUGH
Pre-Inspection 10/21/2024 Corrections Issued JOAQUIN GREENOUGH
Final 10/29/2024 OK to Issue CofO JOAQUIN GREENOUGH
Special/Order Compliance 10/30/2024 Corrections Issued JOAQUIN GREENOUGH