741 W 115TH ST 90044

Certificate Information: 741 W 115TH ST 90044

Application / Permit
22014-10000-04879
Plan Check / Job No.
B22LA19827
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) SFD WITH ADDITION AT THE REAR. RE-STUCCO EXISTING HOUSE, REMODEL EXISTING KITCHEN AND BATH, CHANGE WINDOWS TO LIKE SIZE. "COMPLY WITH DEPARTMENT ORDER effective date 08/18/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/3/2022 FARSHAD ALIMOHAMADI
Corrections Issued 10/3/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 10/3/2022 FARSHAD ALIMOHAMADI
Issued 10/3/2022 APPLICANT
CofO in Progress 3/28/2023 DANIEL GONZALEZ
Permit Finaled 10/2/2025 CLAUDIO MORENO
CofO Issued 10/2/2025 CLAUDIO MORENO
Permit Finaled 10/2/2025 CLAUDIO MORENO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/3/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 10/3/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/7/2022 Not Ready for Inspection KIM DOEPPING
Insulation 10/13/2022 No Access for Inspection DANIEL GONZALEZ
BUILDING-Rough-Frame 10/18/2022 No Access for Inspection KIM DOEPPING
Green Building Rough 10/18/2022 No Access for Inspection KIM DOEPPING
MERV13>=Rough 10/18/2022 No Access for Inspection KIM DOEPPING
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection KIM DOEPPING
Green Building Rough 10/25/2022 Not Ready for Inspection KIM DOEPPING
MERV13>=Rough 10/25/2022 Not Ready for Inspection KIM DOEPPING
ELECTRICAL-Rough 11/2/2022 Corrections Issued DANIEL GONZALEZ
PLUMBING-Rough 11/4/2022 No Access for Inspection KIM DOEPPING
ELECTRICAL-Rough 11/7/2022 Approved KIM DOEPPING
ELECTRICAL-Rough 11/14/2022 Approved DANIEL GONZALEZ
PLUMBING-Rough 11/15/2022 Conditional Approval KIM DOEPPING
BUILDING-Rough-Frame 11/16/2022 Not Ready for Inspection KIM DOEPPING
Insulation 11/16/2022 Approved KIM DOEPPING
MERV13>=Rough 11/16/2022 Not Ready for Inspection KIM DOEPPING
HVAC-Rough 11/17/2022 Conditional Approval KIM DOEPPING
Interior/Exterior Lathing 11/17/2022 Approved KIM DOEPPING
Footing/Foundation/Slab 11/21/2022 Approved KIM DOEPPING
HVAC-Rough 11/21/2022 Approved KIM DOEPPING
PLUMBING-Rough 11/21/2022 Approved KIM DOEPPING
Drywall Nailing 11/23/2022 Not Ready for Inspection DANIEL GONZALEZ
Drywall Nailing 11/29/2022 Approved KIM DOEPPING
Interior/Exterior Lathing 1/10/2023 Approved DANIEL GONZALEZ
PLUMBING-Final 1/17/2023 Not Ready for Inspection DANIEL GONZALEZ
Green Building Rough 2/3/2023 Approved DANIEL GONZALEZ
PLUMBING-Final 2/3/2023 Corrections Issued DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Not Ready DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Not Ready DANIEL GONZALEZ
BUILDING-Rough-Frame 3/23/2023 Approved DANIEL GONZALEZ
ELECTRICAL-Final 3/23/2023 Approved DANIEL GONZALEZ
Final 3/23/2023 OK to Issue CofO DANIEL GONZALEZ
Green Building Final 3/23/2023 Approved DANIEL GONZALEZ
HVAC-Final 3/23/2023 Approved DANIEL GONZALEZ
MERV13>=Final 3/23/2023 Approved DANIEL GONZALEZ
MERV13>=Rough 3/23/2023 Approved DANIEL GONZALEZ
PLUMBING-Final 3/23/2023 Approved DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Approved DANIEL GONZALEZ
Smoke Detectors 3/23/2023 Approved DANIEL GONZALEZ