3479 S MCLAUGHLIN AVE 90066
Certificate Information: 3479 S MCLAUGHLIN AVE 90066
- Application / Permit
- 22014-10000-04877
- Plan Check / Job No.
- B22LA19823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert Existing Garage to ADU per Ordinance LAMC 12.22 A.33 (c)-(d) and one story addition to ADU
- Permit Issued
- Issued on 2/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2022 | VICTOR CHEN |
| Corrections Issued | 10/5/2022 | VICTOR CHEN |
| Building Plans Picked Up | 10/7/2022 | APPLICANT |
| Plan Check Approved | 1/20/2023 | KHUONG TRUONG |
| Issued | 2/13/2023 | APPLICANT |
| CofO in Progress | 5/30/2025 | WILBER ROSALES |
| Permit Finaled | 6/6/2025 | RICHARD STEINBACH |
| CofO Issued | 6/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 11/3/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 11/29/2022 | FREDDY GARCIA |
| Address approval | Cleared | 12/1/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/1/2022 | DINAH GARIN |
| Sewer availability | Cleared | 12/1/2022 | DINAH GARIN |
| Construction near power lines | Cleared | 1/12/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/17/2023 | Partial Approval | JESUS PINEDA |
| Deputy Drilled-In Anchors | 8/7/2023 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Corrections Issued | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 10/24/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 2/14/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/14/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/21/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 2/21/2024 | Approved | BOBBY KEY |
| Green Building Rough | 2/21/2024 | Not Ready for Inspection | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 2/21/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 2/28/2024 | Approved | JESUS PINEDA |
| Rough-Elec/Plmb/HVAC | 2/28/2024 | Approved | JESUS PINEDA |
| Insulation | 3/1/2024 | Corrections Issued | JESUS PINEDA |
| Insulation | 3/4/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/8/2024 | Approved | JESUS PINEDA |
| Shower Pan | 3/27/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/14/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 8/12/2024 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 8/15/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/18/2025 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 4/18/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Final | 4/18/2025 | Corrections Issued | WILBER ROSALES |
| Smoke Detectors | 4/18/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 5/7/2025 | Corrections Issued | BOBBY KEY |
| Final | 5/7/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/7/2025 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 5/7/2025 | Approved | BOBBY KEY |
| HVAC-Final | 5/16/2025 | Approved | WILBER ROSALES |
| Final | 5/20/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 5/20/2025 | Not Ready for Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/20/2025 | SGSOV Not Ready | WILBER ROSALES |
| ELECTRICAL-Final | 5/29/2025 | Approved | WILBER ROSALES |
| Final | 5/29/2025 | OK to Issue CofO | WILBER ROSALES |
| Green Building Final | 5/29/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Approved | WILBER ROSALES |