3479 S MCLAUGHLIN AVE 90066

Certificate Information: 3479 S MCLAUGHLIN AVE 90066

Application / Permit
22014-10000-04877
Plan Check / Job No.
B22LA19823
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Existing Garage to ADU per Ordinance LAMC 12.22 A.33 (c)-(d) and one story addition to ADU
Permit Issued
Issued on 2/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 VICTOR CHEN
Corrections Issued 10/5/2022 VICTOR CHEN
Building Plans Picked Up 10/7/2022 APPLICANT
Plan Check Approved 1/20/2023 KHUONG TRUONG
Issued 2/13/2023 APPLICANT
CofO in Progress 5/30/2025 WILBER ROSALES
Permit Finaled 6/6/2025 RICHARD STEINBACH
CofO Issued 6/6/2025 RICHARD STEINBACH
Permit Finaled 6/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/2/2022 JENSON LEE
Grading Pre-Inspection Cleared 11/3/2022 KIRK LINKLATER
Specific Plan Cleared 11/29/2022 FREDDY GARCIA
Address approval Cleared 12/1/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 12/1/2022 DINAH GARIN
Sewer availability Cleared 12/1/2022 DINAH GARIN
Construction near power lines Cleared 1/12/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/17/2023 Partial Approval JESUS PINEDA
Deputy Drilled-In Anchors 8/7/2023 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 8/11/2023 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 10/24/2023 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 2/14/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 2/14/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/21/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 2/21/2024 Approved BOBBY KEY
Green Building Rough 2/21/2024 Not Ready for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 2/21/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 2/28/2024 Approved JESUS PINEDA
Green Building Rough 2/28/2024 Approved JESUS PINEDA
Rough-Elec/Plmb/HVAC 2/28/2024 Approved JESUS PINEDA
Insulation 3/1/2024 Corrections Issued JESUS PINEDA
Insulation 3/4/2024 Approved JESUS PINEDA
Drywall Nailing 3/8/2024 Approved JESUS PINEDA
Shower Pan 3/27/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 6/14/2024 Approved JESUS PINEDA
Underground Mechanical 8/12/2024 Corrections Issued JESUS PINEDA
Underground Mechanical 8/15/2024 Approved JESUS PINEDA
ELECTRICAL-Final 4/18/2025 Corrections Issued WILBER ROSALES
HVAC-Final 4/18/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 4/18/2025 Corrections Issued WILBER ROSALES
Smoke Detectors 4/18/2025 Approved WILBER ROSALES
ELECTRICAL-Final 5/7/2025 Corrections Issued BOBBY KEY
Final 5/7/2025 Corrections Issued BOBBY KEY
HVAC-Final 5/7/2025 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 5/7/2025 Approved BOBBY KEY
HVAC-Final 5/16/2025 Approved WILBER ROSALES
Final 5/20/2025 Corrections Issued WILBER ROSALES
Green Building Final 5/20/2025 Not Ready for Inspection WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Not Ready WILBER ROSALES
ELECTRICAL-Final 5/29/2025 Approved WILBER ROSALES
Final 5/29/2025 OK to Issue CofO WILBER ROSALES
Green Building Final 5/29/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved WILBER ROSALES