6142 W 76TH ST 90045

Certificate Information: 6142 W 76TH ST 90045

Application / Permit
22014-10000-04871
Plan Check / Job No.
B22LA19805
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 2/17/2023
Issuing Office
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/7/2022 DANIEL YIP
Corrections Issued 10/8/2022 DANIEL YIP
Applicant returned to address corrections 2/2/2023 SAMUEL GONZALEZ
Applicant returned to address corrections 2/10/2023 DANIEL YIP
Plan Check Approved 2/17/2023 DANIEL YIP
Plan Check Approved 2/17/2023 DANIEL YIP
Issued 2/17/2023 APPLICANT
CofO in Progress 6/5/2024 BOBBY KEY
Permit Finaled 6/6/2024 DANIEL ORRANTE
CofO Issued 6/6/2024 DANIEL ORRANTE
Permit Finaled 6/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/25/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/26/2022 DINAH GARIN
Grading Pre-Inspection Cleared 10/26/2022 VASIL MIHALEV
Sewer availability Cleared 10/26/2022 DINAH GARIN
Specific Plan Cleared 12/27/2022 PEDRO AYALA
Roof/Waste drainage to street Cleared 12/30/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/21/2023 Partial Approval HERBERT GIRON
Underground Mechanical 4/21/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 4/27/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/3/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/6/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Corrections Issued BOBBY KEY
HVAC-Rough 7/6/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 7/6/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 7/17/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved BOBBY KEY
HVAC-Rough 7/17/2023 Conditional Approval BOBBY KEY
PLUMBING-Rough 7/17/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 8/9/2023 Corrections Issued BOBBY KEY
Final 8/9/2023 Corrections Issued BOBBY KEY
Insulation 8/9/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 8/9/2023 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 8/17/2023 Approved BOBBY KEY
Insulation 8/17/2023 Approved BOBBY KEY
Interior/Exterior Lathing 8/17/2023 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 8/17/2023 Approved BOBBY KEY
Drywall Nailing 9/8/2023 Approved BOBBY KEY
Interior/Exterior Lathing 9/8/2023 Approved BOBBY KEY
ELECTRICAL-Final 5/29/2024 Approved BOBBY KEY
Final 5/29/2024 Corrections Issued BOBBY KEY
HVAC-Final 5/29/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 5/29/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 5/29/2024 Approved BOBBY KEY
Final 6/4/2024 OK to Issue CofO BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Approved BOBBY KEY