6142 W 76TH ST 90045
Certificate Information: 6142 W 76TH ST 90045
- Application / Permit
- 22014-10000-04871
- Plan Check / Job No.
- B22LA19805
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Current Status
- CofO Issued on 6/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2022 | DANIEL YIP |
| Corrections Issued | 10/8/2022 | DANIEL YIP |
| Applicant returned to address corrections | 2/2/2023 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 2/10/2023 | DANIEL YIP |
| Plan Check Approved | 2/17/2023 | DANIEL YIP |
| Plan Check Approved | 2/17/2023 | DANIEL YIP |
| Issued | 2/17/2023 | APPLICANT |
| CofO in Progress | 6/5/2024 | BOBBY KEY |
| Permit Finaled | 6/6/2024 | DANIEL ORRANTE |
| CofO Issued | 6/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 10/26/2022 | VASIL MIHALEV |
| Sewer availability | Cleared | 10/26/2022 | DINAH GARIN |
| Specific Plan | Cleared | 12/27/2022 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 12/30/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/21/2023 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 4/21/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 4/27/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/6/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 7/6/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 7/6/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 7/17/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 7/17/2023 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 7/17/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/9/2023 | Corrections Issued | BOBBY KEY |
| Final | 8/9/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 8/9/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 8/17/2023 | Approved | BOBBY KEY |
| Insulation | 8/17/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/17/2023 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 8/17/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 9/8/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/8/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/29/2024 | Approved | BOBBY KEY |
| Final | 5/29/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/29/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/29/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 5/29/2024 | Approved | BOBBY KEY |
| Final | 6/4/2024 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | BOBBY KEY |