15919 W TEMECULA ST 90272
Certificate Information: 15919 W TEMECULA ST 90272
- Application / Permit
- 22014-10000-04852
- Plan Check / Job No.
- B22LA19764
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One story, ground floor additions and interior remodel to (E) Single Family Dwelling to extend rear bedroom and living room. All work per engineered design.
- Permit Issued
- Issued on 3/3/2023
- Issuing Office
- Metro
- Current Status
- Issued on 3/3/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | VICTOR CHEN |
| Corrections Issued | 10/4/2022 | VICTOR CHEN |
| Building Plans Picked Up | 10/7/2022 | APPLICANT |
| Applicant returned to address corrections | 2/6/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 2/23/2023 | RAHEL BEYENE |
| Applicant returned to address corrections | 3/2/2023 | SHANGQIN XIE |
| Plan Check Approved | 3/3/2023 | DANIEL SMILEY |
| Issued | 3/3/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 10/12/2022 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 10/18/2022 | KIRK LINKLATER |
| Coastal Zone | Cleared | 12/1/2022 | RUBEN VASQUEZ |
| Construction near power lines | Cleared | 12/17/2022 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 2/6/2023 | VICTOR CHEN |
| Low Impact Development | Cleared | 2/16/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/16/2023 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hanna,, Arsanious Michael; Lic. No.: C70743 | 13408 NAOMA LN CERRITOS, CA 90703 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/29/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 3/31/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/18/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 4/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 4/24/2023 | Approved | BRENDAN LOONEY |
| Special/Order Compliance | 5/16/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 5/16/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 6/5/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 6/5/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/5/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 6/21/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 6/21/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 6/21/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 6/21/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 6/26/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 7/6/2023 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 8/21/2023 | Corrections Issued | EVAN COOPER |
| Final | 8/21/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 8/21/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 8/21/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 8/21/2023 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/21/2023 | Not Ready for Inspection | EVAN COOPER |
| Final | 10/12/2023 | Corrections Issued | EVAN COOPER |
| Final | 10/16/2023 | Corrections Issued | EVAN COOPER |
| Final | 1/11/2024 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 1/11/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 1/11/2024 | Approved | EVAN COOPER |