3660 N LONGVIEW VALLEY ROAD 91423

Certificate Information: 3660 N LONGVIEW VALLEY ROAD 91423

Application / Permit
22014-10000-04844
Plan Check / Job No.
B22LA19716
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* - 5'-8" X 11'5" GROUND FLOOR ADDITION (60 SF) TO (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE. REPLACE AND UPGRADE ALL EXISTING WINDOWS.
Permit Issued
Issued on 2/1/2023
Issuing Office
Current Status
CofO Issued on 7/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 VIVIAN LAO
Corrections Issued 10/6/2022 VIVIAN LAO
Applicant returned to address corrections 1/20/2023 OMAR GARNICA
Plan Check Approved 1/24/2023 OMAR GARNICA
No Progress 1/31/2023 OMAR GARNICA
Plan Check Approved 1/31/2023 OMAR GARNICA
Issued 2/1/2023 APPLICANT
CofO in Progress 6/8/2023 JOHN COLEMAN
Permit Finaled 7/26/2023 RUBEN SALAS
CofO Issued 7/26/2023 RUBEN SALAS
Permit Finaled 7/26/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/28/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/28/2022 LEE GUILBEAUX
Sewer availability Cleared 11/28/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/28/2022 LEE GUILBEAUX
Specific Plan Cleared 12/23/2022 OLGA AYALA
Grading Pre-Inspection Cleared 1/24/2023 OMAR GARNICA

Contact Information

Architect Lee,, Kenneth David; Lic. No.: C10141 16501 ACADEMIA DRIVE      ENCINO, CA 91436
Contractor Points West Construction Inc; Lic. No.: 990740-B 236 SOUTH MYERS STREET      BURBANK, CA 91506
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/10/2023 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 2/14/2023 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/17/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/22/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 2/22/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/21/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 3/21/2023 Approved MISAEL ESPARZA
Green Building Rough 3/21/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/21/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/5/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 4/5/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/5/2023 Corrections Issued MISAEL ESPARZA
Insulation 4/5/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/12/2023 Approved MISAEL ESPARZA
Green Building Rough 4/12/2023 Approved MISAEL ESPARZA
HVAC-Rough 4/12/2023 Approved MISAEL ESPARZA
Insulation 4/12/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/12/2023 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 4/19/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 4/27/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/27/2023 Partial Approval MISAEL ESPARZA
Shower Pan 4/27/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/3/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/7/2023 Approved JOHN COLEMAN
Final 6/7/2023 OK to Issue CofO JOHN COLEMAN
Footing/Foundation/Slab 6/7/2023 Approved JOHN COLEMAN
Green Building Final 6/7/2023 Approved JOHN COLEMAN
HVAC-Final 6/7/2023 Approved JOHN COLEMAN
PLUMBING-Final 6/7/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Approved JOHN COLEMAN
Smoke Detectors 6/7/2023 Approved JOHN COLEMAN