668 N JACON WAY 90272
Certificate Information: 668 N JACON WAY 90272
- Application / Permit
- 22014-10000-04812
- Plan Check / Job No.
- B22LA19555
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st and 2nd story addition to and renovation of (E) 1-story SFD with attached garage with steel posts & beams.
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | TSE MING HUANG |
| Corrections Issued | 10/4/2022 | TSE MING HUANG |
| Quality Review Completed | 10/6/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/16/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 11/30/2022 | TSE MING HUANG |
| Plan Check Approved | 3/30/2023 | TSE MING HUANG |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 10/25/2024 | EVAN COOPER |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| CofO Issued | 11/12/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/24/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 10/24/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 10/24/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 10/24/2022 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 10/24/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 11/3/2022 | JENSON LEE |
| Coastal Zone | Cleared | 11/8/2022 | RUBEN VASQUEZ |
| ZI | Cleared | 11/8/2022 | RUBEN VASQUEZ |
| Grading Pre-Inspection | Cleared | 11/16/2022 | TSE MING HUANG |
| Hydrant and Access approval | Cleared | 11/25/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 3/22/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/28/2023 | JASON NG |
Contact Information
| Architect | , ; Lic. No.: C34496 | , |
| Contractor | M Construction Inc; Lic. No.: 1025376-B | 365 E.AVENIDA DEL LOS ARBOLES #217 THOUSAND OAKS, CA 91360 |
| Engineer | Chen,, Duncan; Lic. No.: C81058 | 5690 SCHAEFER AVE #A CHINO, CA 91710 |
| Engineer | Djoneva,, Diana Ivanova; Lic. No.: C73805 | 3241 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/24/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 6/8/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/20/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/2/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 8/11/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 8/15/2023 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/15/2023 | Not Ready for Inspection | EVAN COOPER |
| Structural Steel Frame | 8/15/2023 | Partial Approval | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/15/2023 | Not Ready for Inspection | EVAN COOPER |
| Deputy Wood Construction | 9/5/2023 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Partial Approval | EVAN COOPER |
| Deputy Steel/Welding | 10/12/2023 | Conditional Approval | EVAN COOPER |
| Deputy Wood Construction | 11/9/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 11/16/2023 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 11/17/2023 | Approved | EVAN COOPER |
| Deputy Wood Construction | 12/12/2023 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 12/13/2023 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 2/7/2024 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 2/7/2024 | Approved | EVAN COOPER |
| Green Building Rough | 2/7/2024 | Approved | EVAN COOPER |
| HVAC-Rough | 2/7/2024 | Corrections Issued | EVAN COOPER |
| Verify Sprinkler Sign Off | 2/7/2024 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 2/14/2024 | Approved | EVAN COOPER |
| Final | 2/14/2024 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 2/14/2024 | Approved | EVAN COOPER |
| PLUMBING-Rough | 2/14/2024 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 2/14/2024 | Approved | EVAN COOPER |
| Insulation | 2/26/2024 | Approved | EVAN COOPER |
| Shower Pan | 2/26/2024 | Not Ready for Inspection | EVAN COOPER |
| Drywall Nailing | 3/11/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | EVAN COOPER |
| Shower Pan | 4/11/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/26/2024 | Approved | EVAN COOPER |
| Gas Test | 9/5/2024 | Approved | EVAN COOPER |
| Service/Power Release | 9/5/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 9/24/2024 | Not Ready for Inspection | EVAN COOPER |
| Pre-Inspection | 9/24/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/1/2024 | Approved | EVAN COOPER |
| Final | 10/1/2024 | Corrections Issued | EVAN COOPER |
| Green Building Final | 10/1/2024 | Approved | EVAN COOPER |
| HVAC-Final | 10/1/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 10/1/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 10/1/2024 | Approved | EVAN COOPER |
| Final | 10/25/2024 | OK to Issue CofO | EVAN COOPER |