528 1/4 N VISTA ST 90036

Certificate Information: 528 1/4 N VISTA ST 90036

Application / Permit
22014-10000-04802
Plan Check / Job No.
B22LA19472
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 5/8/2023
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 DANIEL YIP
Corrections Issued 10/6/2022 DANIEL YIP
Applicant returned to address corrections 11/14/2022 HANS SANTIAGO
Plan Check Approved 4/7/2023 DANIEL YIP
Issued 5/8/2023 APPLICANT
CofO in Progress 8/29/2024 ENRIQUE MIRELES
Permit Finaled 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/5/2022 STEVE MELGAR
Address approval Cleared 12/14/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 12/20/2022 STEVE MELGAR
Sewer availability Cleared 12/20/2022 STEVE MELGAR
Construction near power lines Cleared 3/18/2023 RIDWAN HARDY

Contact Information

Contractor Right Choice Renovation Inc; Lic. No.: 1066263-B       ,
Engineer Morales,, Cesar Del Valle; Lic. No.: C76612 11735 THORSON AVE      LYNWOOD, CA 90262

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/11/2023 Partial Approval LILIANA PORTILLO
METHANE-Barrier 5/11/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 5/11/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 5/11/2023 Partial Approval LILIANA PORTILLO
Sewer 5/11/2023 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 5/16/2023 No Access for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 5/18/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 7/31/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 7/31/2023 Not Ready for Inspection LILIANA PORTILLO
Wood Frame 7/31/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 8/1/2023 No Access for Inspection LILIANA PORTILLO
PLUMBING-Rough 8/1/2023 No Access for Inspection LILIANA PORTILLO
Wood Frame 8/1/2023 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 8/10/2023 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 8/10/2023 Not Ready for Inspection LILIANA PORTILLO
Underground Mechanical 8/10/2023 Corrections Issued LILIANA PORTILLO
Pre-Inspection 8/16/2023 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 9/21/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 9/29/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 9/29/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 10/4/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/4/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/12/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 10/31/2023 Not Ready for Inspection LILIANA PORTILLO
Insulation 10/31/2023 Corrections Issued LILIANA PORTILLO
Drywall Nailing 11/14/2023 Corrections Issued LILIANA PORTILLO
Green Building Rough 11/14/2023 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 11/14/2023 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 11/27/2023 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 11/30/2023 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/7/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 1/19/2024 Approved LILIANA PORTILLO
Shower Pan 1/19/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/13/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 5/13/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Final 5/13/2024 Corrections Issued AMIR NAZARIAN
Final 5/13/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 5/13/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 5/13/2024 Corrections Issued AMIR NAZARIAN
HVAC-Final 5/13/2024 Corrections Issued AMIR NAZARIAN
METHANE-Final 5/13/2024 Corrections Issued AMIR NAZARIAN
METHANE-Rough 5/13/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Final 5/13/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 5/13/2024 SGSOV Not Ready AMIR NAZARIAN
Smoke Detectors 5/13/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 6/18/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 6/18/2024 Corrections Issued AMIR NAZARIAN
Final 6/18/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 6/18/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 6/18/2024 Corrections Issued AMIR NAZARIAN
METHANE-Final 6/18/2024 Approved AMIR NAZARIAN
METHANE-Rough 6/18/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready AMIR NAZARIAN
Smoke Detectors 6/18/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 7/2/2024 Not Ready for Inspection AMIR NAZARIAN
Drywall Nailing 7/2/2024 Not Ready for Inspection AMIR NAZARIAN
Final 7/2/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 7/2/2024 Not Ready for Inspection AMIR NAZARIAN
Green Building Rough 7/2/2024 Not Ready for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Not Ready AMIR NAZARIAN
ELECTRICAL-Final 7/18/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Final 7/22/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 8/26/2024 Approved ENRIQUE MIRELES
Drywall Nailing 8/26/2024 Approved ENRIQUE MIRELES
Final 8/26/2024 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 8/26/2024 Approved ENRIQUE MIRELES
Green Building Rough 8/26/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 8/26/2024 Approved ENRIQUE MIRELES