2724 W RANGE ROAD 90065
Certificate Information: 2724 W RANGE ROAD 90065
- Application / Permit
- 22014-10000-04794
- Plan Check / Job No.
- B22LA19432
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN CONVERT UNDERFLOOR AREA TO NEW FLOOR AREA AND EXISTING 2 STORY HOME RENOVATION
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 10/29/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 11/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 3/3/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 4/6/2023 | MARCELA FRANQUEZ |
| Issued | 4/27/2023 | APPLICANT |
| CofO in Progress | 7/10/2024 | CRAIG VAUGHAN |
| No Progress | 8/8/2024 | CHARLES BOGHOSKHAN |
| CofO in Progress | 8/8/2024 | CHARLES BOGHOSKHAN |
| CofO in Progress | 8/29/2024 | CRAIG VAUGHAN |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/16/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 12/16/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 12/16/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 12/16/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 12/16/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/16/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 1/28/2023 | KURT CORRAL |
| GPI Written Notices | Cleared | 3/3/2023 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 3/3/2023 | MARCELA FRANQUEZ |
Contact Information
| Architect | Sundius,, Bo Kyle; Lic. No.: C38566 | 1814 BROOKS AVE LOS ANGELES, CA 90012 |
| Contractor | M S Elite General Construction Inc; Lic. No.: 660454-B | , |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/11/2023 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/15/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Concrete | 5/16/2023 | Conditional Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/12/2023 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 7/14/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 7/20/2023 | Conditional Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/28/2023 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 8/3/2023 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/11/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 10/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/27/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/31/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 10/31/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/2/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 11/2/2023 | Approved | CRAIG VAUGHAN |
| MERV13>=Rough | 11/2/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/16/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 11/16/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/16/2023 | Approved | CRAIG VAUGHAN |
| Shower Pan | 11/16/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/6/2023 | Approved | CRAIG VAUGHAN |
| Gas Test | 12/6/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/10/2024 | Approved | CRAIG VAUGHAN |
| Final | 5/10/2024 | Conditional Approval | CRAIG VAUGHAN |
| Green Building Final | 5/10/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/10/2024 | Approved | CRAIG VAUGHAN |
| MERV13>=Final | 5/10/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/10/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/10/2024 | Approved | CRAIG VAUGHAN |
| Final | 5/13/2024 | Corrections Issued | CRAIG VAUGHAN |
| Final | 7/9/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Inspection | CHARLES BOGHOSKHAN |
| Final | 8/28/2024 | OK to Issue CofO | CRAIG VAUGHAN |