225 S BARLOCK AVE 90049

Certificate Information: 225 S BARLOCK AVE 90049

Application / Permit
22014-10000-04780
Plan Check / Job No.
B22LA19346
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) SFD RENOVATION AND ADDITION
Permit Issued
Issued on 10/5/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 KHUONG TRUONG
Corrections Issued 10/2/2022 KHUONG TRUONG
Building Plans Picked Up 10/5/2022 APPLICANT
Applicant returned to address corrections 11/10/2022 SAMUEL GONZALEZ
Plan Check Approved 11/23/2022 KHUONG TRUONG
Issued 10/5/2023 APPLICANT
CofO in Progress 8/13/2025 CARLOS MATAMOROS
Permit Finaled 8/27/2025 RICHARD STEINBACH
CofO Issued 8/27/2025 RICHARD STEINBACH
Permit Finaled 8/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 10/22/2022 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 11/14/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 11/14/2022 DINAH GARIN
Grading Pre-Inspection Cleared 11/23/2022 KHUONG TRUONG

Contact Information

Contractor Owner-Builder       ,
Engineer Minn,, Wenchung; Lic. No.: C42605 3358 W 157TH ST      GARDENA, CA 90249

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/20/2023 Partial Approval CARLOS MATAMOROS
Masonry Wall/Backfill 12/8/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 4/30/2024 Corrections Issued CARLOS MATAMOROS
Special/Order Compliance 7/2/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 9/4/2024 Approved CARLOS MATAMOROS
Gas Test 9/4/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/4/2024 Approved CARLOS MATAMOROS
Deputy Wood Construction 9/9/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Approved CARLOS MATAMOROS
HVAC-Rough 9/17/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 9/24/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 10/1/2024 Approved CARLOS MATAMOROS
Deputy Wood Construction 10/3/2024 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/8/2024 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 10/8/2024 Approved CARLOS MATAMOROS
Wood Frame 10/8/2024 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 10/10/2024 Approved STEPHANIE SWANSON
Green Building Rough 10/10/2024 Approved STEPHANIE SWANSON
Insulation 10/22/2024 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 10/25/2024 Approved CARLOS MATAMOROS
Shower Pan 10/25/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 10/29/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 10/29/2024 Approved CHRISTOPHER WILSON
Drywall Nailing 11/7/2024 Approved CARLOS MATAMOROS
Pre-Inspection 2/25/2025 Corrections Issued CHRISTOPHER WILSON
Final 6/16/2025 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 6/16/2025 Approved MEL KHACHATOURIAN
Green Building Final 6/16/2025 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 6/16/2025 Approved MEL KHACHATOURIAN
Final 7/3/2025 Corrections Issued DANIEL VERA
ELECTRICAL-Final 8/13/2025 Approved CARLOS MATAMOROS
Final 8/13/2025 OK to Issue CofO CARLOS MATAMOROS
HVAC-Final 8/13/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 8/13/2025 Approved CARLOS MATAMOROS