12639 W VICTORY BLVD 91606
Certificate Information: 12639 W VICTORY BLVD 91606
- Application / Permit
- 22014-10000-04767
- Plan Check / Job No.
- B22LA19314
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage to a new ADU (366SF)
- Permit Issued
- Issued on 3/13/2023
- Issuing Office
- Current Status
- Issued on 3/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2022 | JOE VO |
| Corrections Issued | 11/16/2022 | JOE VO |
| Plan Check Approved | 3/10/2023 | JOE VO |
| Issued | 3/13/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/9/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/9/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 3/1/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/2/2023 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 3/2/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 7/19/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 7/25/2023 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| Insulation | 8/2/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/9/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 8/9/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 8/9/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/22/2023 | Corrections Issued | KIRK SANDERS |
| Insulation | 8/22/2023 | Partial Approval | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 8/22/2023 | Corrections Issued | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 8/31/2023 | Conditional Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/20/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/20/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | KIRK SANDERS |
| Insulation | 10/5/2023 | Corrections Issued | KIRK SANDERS |
| Insulation | 10/13/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 11/1/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 12/27/2023 | No Access for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 12/27/2023 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 1/18/2024 | Corrections Issued | JOSE AVILA |
| Sewer | 1/18/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 1/18/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 1/23/2024 | Corrections Issued | JOSE AVILA |
| Gas Test | 1/23/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 1/23/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 1/26/2024 | Approved | JOSE AVILA |
| Final | 1/26/2024 | Partial Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 1/26/2024 | Approved | JOSE AVILA |