4060 W MARATHON ST 90029
Certificate Information: 4060 W MARATHON ST 90029
- Application / Permit
- 22014-10000-04761
- Plan Check / Job No.
- B22LA19287
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert Existing Detached 1-story Garage to Accessory Dwelling Unit with Addition Per State Law
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | PRANITA SHAH |
| Corrections Issued | 10/5/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 11/3/2022 | JOE VO |
| Plan Check Approved | 11/19/2022 | JOE VO |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 7/14/2023 | FREDDIE RIVERA |
| CofO Issued | 7/24/2023 | DEROLD HAUFF |
| Permit Finaled | 7/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/18/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 10/19/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | JEANIE LAM |
| Sewer availability | Cleared | 10/31/2022 | JEANIE LAM |
| Specific Plan | Cleared | 11/17/2022 | DANALYNN DOMINGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/6/2022 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 12/6/2022 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 12/12/2022 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/12/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 1/30/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/31/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 1/31/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/3/2023 | Approved | FREDDIE RIVERA |
| Insulation | 2/3/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/6/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/6/2023 | Approved | FREDDIE RIVERA |
| Final | 7/3/2023 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 7/3/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 7/3/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 7/3/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 7/3/2023 | Approved | FREDDIE RIVERA |
| Final | 7/11/2023 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 7/11/2023 | Approved | FREDDIE RIVERA |
| Service/Power Release | 7/11/2023 | Approved | FREDDIE RIVERA |