5503 N COSTELLO AVE 91401
Certificate Information: 5503 N COSTELLO AVE 91401
- Application / Permit
- 22014-10000-04734
- Plan Check / Job No.
- B22LA19162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'x17'-6" addition, interior and exterior alteration to existing one story single family dewlling with attached garage per engineer design and detials
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | AUNG SOE |
| Corrections Issued | 10/4/2022 | AUNG SOE |
| Building Plans Picked Up | 10/5/2022 | APPLICANT |
| Plan Check Approved | 11/8/2022 | ZAW HAN |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 2/7/2023 | RYAN SALAZAR |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
| CofO Issued | 2/17/2023 | MICHAEL SMITH |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/12/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/13/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 11/5/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2022 | Approved | WILLIAM WREN |
| HVAC-Rough | 11/29/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/29/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/5/2022 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 12/5/2022 | Approved | RYAN SALAZAR |
| Wood Frame | 12/5/2022 | Approved | RYAN SALAZAR |
| Insulation | 12/8/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/8/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 12/12/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/18/2023 | Approved | RYAN SALAZAR |
| Final | 1/18/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/18/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 1/18/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/18/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/18/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/7/2023 | Approved | RYAN SALAZAR |
| Final | 2/7/2023 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 2/7/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 2/7/2023 | Approved | RYAN SALAZAR |