2020 N GATES ST 90031
Certificate Information: 2020 N GATES ST 90031
- Application / Permit
- 22014-10000-04712
- Plan Check / Job No.
- B22LA19070
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan 1st AND 2ND FLOOR ADDITION TO (E) ONE STORY ACC. BLDG WITH ATT. 2-CAR GARAGE TO PROPOSE A NEW DET. ADU PER LAMC 12.22 A.33 (c) -(d) & ATT. (E) 1-CAR GARAGE.
- Permit Issued
- Issued on 8/9/2024
- Issuing Office
- Current Status
- Issued on 8/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/14/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/25/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 4/12/2023 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 5/10/2023 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/5/2023 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 5/25/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/25/2024 | MAHNAZ NOURHASHEMI |
| Issued | 8/9/2024 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/4/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 5/8/2024 | LUIS LUVANO |
| Address approval | Cleared | 6/3/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | ANTHONY TRAN |
| Sewer availability | Cleared | 6/3/2024 | ANTHONY TRAN |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | R E T Construction Corp; Lic. No.: 1019820-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2024 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 9/16/2024 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 11/14/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 11/14/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/19/2024 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/11/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 2/11/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 2/11/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/11/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | ANTHONY RAMOS |
| Shower Pan | 2/20/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | ANTHONY RAMOS |
| Gas Test | 2/25/2025 | Partial Approval | ANTHONY RAMOS |
| Insulation | 2/25/2025 | Partial Approval | ANTHONY RAMOS |
| Interior/Exterior Lathing | 2/25/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 2/28/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 6/26/2025 | Approved | ALIZAH MAYAGOITIA |