NEW 2 DETACHED ADUs PER MULTIPLE ADUs (2-STORY) Gov't Code 65852.2(e)(1)(D)
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
CofO Issued on 12/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 CARLOS MONTES
Corrections Issued 10/19/2022 CARLOS MONTES
Quality Review Completed 11/4/2022 PRANITA SHAH
Applicant returned to address corrections 12/13/2022 CARLOS MONTES
Applicant returned to address corrections 4/25/2024 CARLOS MONTES
Applicant returned to address corrections 6/5/2024 CARLOS MONTES
Applicant returned to address corrections 8/1/2024 SAM CHANG
Plan Check Approved 9/25/2024 SAM CHANG
Issued 10/17/2024 APPLICANT
CofO in Progress 12/10/2025 EVAN COOPER
Permit Finaled 12/24/2025 RICHARD STEINBACH
CofO Issued 12/24/2025 RICHARD STEINBACH
Permit Finaled 12/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/30/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/6/2023 JEANIE LAM
Sewer availability Cleared 5/30/2023 JEANIE LAM
Construction near power lines Cleared 8/2/2023 TINA MIRANDA
Low Impact Development Cleared 2/2/2024 ROGELIO CORTES
Roof/Waste drainage to street Cleared 2/5/2024 ARNULFO CHAMU
Address approval Cleared 8/26/2024 JUSTIN BICOL

Contact Information

Contractor Interserve Construction Corp; Lic. No.: 968925-B 8023 BEVERLY BLVD STE1 #1139      LOS ANGELES, CA 90048
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2025 Partial Approval EVAN COOPER
Footing/Foundation/Slab 4/28/2025 Approved MEL KHACHATOURIAN
METHANE-Barrier 4/28/2025 Approved MEL KHACHATOURIAN
METHANE-Subgrade 4/28/2025 Approved MEL KHACHATOURIAN
Deputy Wood Construction 5/9/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 6/10/2025 Approved EVAN COOPER
HVAC-Rough 6/10/2025 Corrections Issued EVAN COOPER
Service/Power Release 6/10/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 6/20/2025 Conditional Approval EVAN COOPER
Green Building Rough 6/20/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 6/20/2025 Approved EVAN COOPER
Wood Frame 6/20/2025 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 6/30/2025 Approved ARAM AVEDISIAN
Green Building Rough 6/30/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/30/2025 Partial Approval ARAM AVEDISIAN
Insulation 7/8/2025 Approved EVAN COOPER
Shower Pan 7/8/2025 Approved EVAN COOPER
Interior/Exterior Lathing 7/11/2025 Approved EVAN COOPER
Drywall Nailing 7/14/2025 Approved EVAN COOPER
Gas Test 8/18/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 8/18/2025 Not Ready for Inspection DANIEL VERA
Underground Mechanical 8/18/2025 Corrections Issued DANIEL VERA
Gas Test 8/19/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 8/19/2025 Not Ready for Inspection DANIEL VERA
Underground Mechanical 8/19/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 8/26/2025 Approved EVAN COOPER
Sewer 8/26/2025 Partial Approval EVAN COOPER
Underground Mechanical 8/26/2025 Partial Approval EVAN COOPER
ELECTRICAL-Final 9/17/2025 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 10/1/2025 Approved EVAN COOPER
Final 10/1/2025 Corrections Issued EVAN COOPER
Green Building Final 10/1/2025 Approved EVAN COOPER
HVAC-Final 10/1/2025 Approved EVAN COOPER
PLUMBING-Final 10/1/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 10/1/2025 Approved EVAN COOPER
Service/Power Release 10/2/2025 Approved EVAN COOPER
Final 12/5/2025 OK to Issue CofO EVAN COOPER
Special/Order Compliance 12/10/2025 Approved EVAN COOPER