8336 S STEWART AVE 90045
Certificate Information: 8336 S STEWART AVE 90045
- Application / Permit
- 22014-10000-04686
- Plan Check / Job No.
- B22LA18960
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Irregular addition to front (68 sqft + 69 sqft porch) and rear (571 sqft) of existing 1-story single family dwelling with interior remodel for kitchen and bathrooms. Work per engineering. **ePLAN**
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Current Status
- CofO Issued on 11/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2022 | DANIEL SANJUAN |
| Corrections Issued | 9/28/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 11/15/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 1/30/2023 | VICTOR CHEN |
| Plan Check Approved | 2/19/2023 | ISIS ARGUETA |
| Issued | 2/21/2023 | APPLICANT |
| CofO in Progress | 10/29/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
| CofO Issued | 11/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/11/2022 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | JENSON LEE |
| Low Impact Development | Cleared | 11/3/2022 | DEBORA LEITE |
| Sewer availability | Cleared | 11/9/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 11/10/2022 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2023 | Partial Inspection | BOBBY KEY |
| Underground Mechanical | 4/20/2023 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 5/11/2023 | Partial Inspection | BOBBY KEY |
| Deputy Drilled-In Anchors | 5/16/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 5/16/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/5/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 7/11/2023 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 7/11/2023 | Not Ready for Inspection | BOBBY KEY |
| Underground Mechanical | 7/11/2023 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 7/17/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 7/18/2023 | Approved | BOBBY KEY |
| Gas Test | 7/18/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 7/18/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 7/19/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/12/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 10/12/2023 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 10/24/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/24/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/9/2024 | Approved | BOBBY KEY |
| Insulation | 1/9/2024 | Corrections Issued | BOBBY KEY |
| Insulation | 1/19/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/29/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 10/30/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 10/30/2024 | Approved | TEMISTOCLES CAAL |
| Pre-Inspection | 5/9/2025 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 7/25/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 9/3/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 9/8/2025 | Approved | JESUS PINEDA |
| Service/Power Release | 9/8/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 10/20/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/20/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/20/2025 | Approved | JESUS RODRIGUEZ |
| Final | 10/28/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 10/28/2025 | Approved | JESUS RODRIGUEZ |